JFC Construction Update - Construction Progress - Issue 33 - 9 March 2020 CONSTRUCTION UPDATERead our construction update to see what has been achieved and what is coming up on the Karangahape Road Enhancements project. Symonds Street to Upper Queen StreetUpcoming works - what to expect:
Upper Queen Street to Mercury LaneWork has progressed well over the last week with large sections of the paving completed. Upcoming works - what to expect:
Ponsonby Road to Hereford StreetLast week, the surface of Hereford Street was re-asphalted and line-marked, including the loading zone. The lane closure on Hereford Street has been removed and is now back open to two-way traffic. Upcoming night works - what to expect:
Photo: Hereford Street ashaplting and linemarking complete. Hereford Street to Howe StreetUpcoming works - what to expect:
Howe Street to the OverbridgeUpcoming works - what to expect: Howe Street works include:
Upcoming night works - what to expect:
OverbridgeWorks on the overbridge is progressing well with the second bus shelter and glass installed. Upcoming works - what to expect:
STAGING & LOADING ZONESBelow is a map of the Karangahape Road precinct showing the construction stages, temporary bus stop relocations and loading zones. Work was expected to commence in the section from Symonds Street to Queen Street today. We are still awaiting traffic management approval to start work, therefore this section is now expected to start later this week. For most of this stage, construction is in the carriageway and the outer edge of the footpath, however there will be footpath reconstruction on the intersections at Liverpool Street and Queen Street. The bus stop at this location will also be removed but service will be maintained along Karangahape Road. Auckland Transport’s parking enforcement is working to ensure parking is being correctly used throughout the Karangahape Road precinct. If you have a request for parking enforcement, please call Auckland Council on 09 301 0101. Please find a link here to a larger version of the below image. If you have any construction queries during the project, we encourage you to contact us on |