JFC Construction Update - Construction Progress - Issue 40 - 2 June 2020

 

CONSTRUCTION UPDATE

Read our construction update to see what has been achieved and what is coming up on the Karangahape Road Enhancements project. 

 

Symonds Street to Queen Street

Upcoming works - what to expect:

  • Finalise the kerb stone and cycle lane kerb installation at the Symonds Street corner 

  • Continue with underground services installation and drainage in the section between Liverpool Street and Queen Street

  • Continue with speed table installation at Liverpool Street and prepare mesh and steel for concrete pour

  • Continue with kerb stone and cycle lane kerb installation between Liverpool and Queen Street

Photo: Speed table under construction

 
 

Photo: Kerb stones being installed

Upper Queen Street to Mercury Lane

Upcoming works - what to expect:

  • Finalise kerb stones and cycleway at the Upper Queen Street corner

Upcoming night works - what to expect:

These night works are taking place one evening this week due to high pedestrian numbers.  Footpath access will be maintained around the work. 

  • Lift pavers and prepare surface for new pavers at the ANZ corner.   Please note there will be intermittent medium to high volume noise, i.e. trucks loading and rock breakers, but we will endeavour to have noisy works completed by 10:30pm.  This work is expected to take approximately 4 hours
  • Pedestrian flow around this corner will be changed to accommodate the paving work  
 

Mercury Lane to West Terrace

Upcoming works - what to expect:

  • Continue construction in the carriageway and the outer edge of the footpath
  • Relocate the existing traffic control box to a temporary location - this will be moved to next week
  • Continue with rain garden installation
  • Continue with stormwater drainage construction and installation of new ducting
  • Continue laying cycleway and kerbline 

Temporary Traffic management change - East Street:

At the end of this week we will be installing new ducts across East Street.  In order for this to be done without closing the road, we will be reducing East Street to one lane at the Karanagahape Road intersection.  This means that we will have a Stop/Go operation in place for the duration of this work.  This is expected to take one week.  We will return late June to construct the speed table. 

Upcoming night works what to expect:

On Sunday night, 7 June night works is taking place at the pedestrian crossing.  This is in the section between West Terrace and East Street at the Day Street crossing.

These night works are taking place in the evening due to high pedestrian and vehicle numbers as changes to the traffic lights are required.  Vehicle and footpath access will be maintained around the work.

The existing traffic light will be removed and put onto a drum so that work on the kerbline can continue.  This work will only take one night to complete.  Please note there will be intermittent medium to high volume noise, i.e. grinding but we will endeavour to have noisy works completed by 10:30pm

 

Overbridge

The steel work for the overbridge is under construction and is expected to be complete by late June.  

 

Hereford Street to Howe Street

The traffic management plans allow for work on one side of Howe Street at a time.  We have exposed the existing services and have also commenced installation of new ducting in this location.  Work on this corner is pending relocation of services by asset owners to allow our works to continue.

Photo: Existing services exposed

 

STAGING & LOADING ZONES  

Below is a map of the Karangahape Road precinct showing the construction stages, temporary bus stop relocations and loading zones.

Auckland Transport’s parking enforcement is working to ensure parking is being correctly used throughout the Karangahape Road precinct.  If you have a request for parking enforcement, please call Auckland Council on 09 301 0101.

Loading zone map below 

 

If you have any construction queries during the project, we encourage you to contact us on 
0800 KRD JFC (0800 573 532) or karangahaperoad@jfcltd.co.nz

 

If you know of anyone who would like to receive these updates, feel free to forward this email to them and get them to subscribe via the link below. Or email us at karangahaperoad@jfcltd.co.nz 