JFC Construction Update - Construction Progress - Issue 20 - 7 January 2020 CONSTRUCTION UPDATERead our construction update to see what has been achieved and what is coming up on the Karangahape Road Enhancements project. Upper Queen Street to Mercury LaneUpcoming works - what to expect:
Upcoming night works - what to expect:
These works are scheduled for the evening when traffic volumes are lower, as changes to the road layout and traffic management are required. Vehicle access on Karangahape Road and Upper Queen Street will still be available - please follow the signage. Ponsonby Road to Hereford StreetUpcoming works - what to expect:
Hereford Street to Howe StreetUpcoming works - what to expect:
Upcoming night works - what to expect:
This work is scheduled for the evening when traffic volumes are lower, as changes to the road layout and traffic management are required. Vehicle access on Karangahape Road and Howe Street will still be available - please follow the signage. Howe Street to OverbridgeUpcoming works - what to expect:
OverbridgeUpcoming works - what to expect:
Access
Photo: new paving delineation of the cycleway installed on the northern side of the overbridge. STAGING & LOADING ZONESBelow is a map of the Karangahape Road precinct showing the construction stages, temporary bus stop relocations and loading zones. The Auckland Transport project team are working closely with their parking enforcement team to monitor locations to ensure they're being correctly used. If you have a request for parking enforcement, please call Auckland Council on 09 301 0101. Please find a link here to a larger version of the below image. If you have any construction queries during the project, we encourage you to contact us on If you know of anyone who would like to receive these updates, feel free to forward this email to them and get them to subscribe via the link below. Or email us at karangahaperoad@jfcltd.co.nz |