JFC Construction Update - Construction Progress - Issue 24 - 20 January 2020 CONSTRUCTION UPDATERead our construction update to see what has been achieved and what is coming up on the Karangahape Road Enhancements project. Upper Queen Street to Mercury LaneConstruction progressed well last week with ducting and kerblines installed and the blockwork walls complete on the first two raingardens. Upcoming works - what to expect:
Ponsonby Road to Hereford StreetWorks to move the traffic lane of Hereford Street were successfully undertaken and significant drainage works were completed in the carriageway. Upcoming works - what to expect:
Upcoming night works:
Hereford Street to Howe StreetThe traffic islands, separating the cycleway and the road are mostly paved in this section, and a large portion of the cycleway has been asphalted. Upcoming works - what to expect:
Upcoming night works:
Howe Street to OverbridgeUpcoming works - what to expect:
OverbridgeUpcoming works - what to expect:
Access
STAGING & LOADING ZONESBelow is a map of the Karangahape Road precinct showing the construction stages, temporary bus stop relocations and loading zones. The Auckland Transport project team are working closely with their parking enforcement team to monitor locations to ensure they're being correctly used. If you have a request for parking enforcement, please call Auckland Council on 09 301 0101. Please find a link here to a larger version of the below image. If you have any construction queries during the project, we encourage you to contact us on If you know of anyone who would like to receive these updates, feel free to forward this email to them and get them to subscribe via the link below. Or email us at karangahaperoad@jfcltd.co.nz |