JFC Construction Update - Construction Progress - Issue 30 - 17 February 2020 CONSTRUCTION UPDATERead our construction update to see what has been achieved and what is coming up on the Karangahape Road Enhancements project. Upper Queen Street to Mercury LaneUpcoming works - what to expect:
Photo: Cycleway prepared ready for asphalt later in the week Ponsonby Road to Hereford StreetOver the weekend a temporary road surface was created for vehicles to exit Hereford Street. This is so that works could commence on the remaining section of the speed table across Hereford Street today. Upcoming works - what to expect:
Hereford Street to Howe StreetWorks have progressed well over the last week with the first half of the concrete speedtable and cycleway at the intersection of Hereford Street finished. The rain garden on the corner of Howe street was also completed last week. Upcoming works - what to expect:
Howe Street to OverbridgeUpcoming works - what to expect:
Upcoming night works - what to expect:
OverbridgeThe framing for the first sections of the bus stop shelters have been installed Upcoming works - what to expect:
Access - Reminder
Photo: Framing up for first section of bus stop shelters STAGING & LOADING ZONESBelow is a map of the Karangahape Road precinct showing the construction stages, temporary bus stop relocations and loading zones. The Auckland Transport project team are working closely with their parking enforcement team to monitor locations to ensure they're being correctly used. If you have a request for parking enforcement, please call Auckland Council on 09 301 0101. If you have any construction queries during the project, we encourage you to contact us on If you know of anyone who would like to receive these updates, feel free to forward this email to them and get them to subscribe via the link below. Or email us at karangahaperoad@jfcltd.co.nz |