JFC Construction Update - Construction Progress - Issue 63 - 9 November 2020

 

CONSTRUCTION UPDATE

Read our construction update to see what has been achieved and what is coming up on the Karangahape Road Enhancements project. 

 

Symonds Street to Liverpool Street

This week we plan to move to the intersection of Symonds Street and Karangahape Road to complete the new street light and traffic light installation, and construct the new pram crossing.   

 

Liverpool Street to Queen Street 

Additional relocation works by utility providers of the exposed services on the corner of Queen Street have been completed.     

Upcoming works - what to expect: 

  • Finalise cycle lane
 

Queen Street to Pitt Street

This week we plan to commence works on the intersection of Pitt Street and Karangahape Road to construct the new kerb line, new pram crossing and finalise the street light and traffic light installation.

The bus stop between Pitt Street and the mid block pedestrian crossing will be opened up this week.

Upcoming works - what to expect: 

  • Saw cut carriageway and commence demolition of carriageway and footpath at Pitt Street corner
  • Install permanent lights on new foundations
  • Prepare for cycleway concrete from the mid block pedestrian crossing towards Queen Street
  • Install traffic lights at mid block crossing
 
 

Photo: Pohutakawa Mistral tree planted near mid block pedestrian crossing

 

Mercury Lane to West Terrace

Upcoming works - what to expect:

  • Commence construction of the new pram crossing towards Pitt Street, and install paving and tactiles at Mercury Lane corner
  • Cutover fibre to new traffic control box at West Terrace/Day Street crossing
  • Transfer signal cables from the old traffic light cabinet to the new cabinet at West Terrace/Day Street crossing
 

Cobden Street to Edinburgh Street

Upcoming works - what to expect: 

  • Continue with raingarden construction  
  • Continue with ducting and kerbline installation

Change in temporary traffic management - Cobden Street 

To undertake drainage activities, this week, Cobden Street will temporarily be down to one lane. Two way access will be allowed via a signalised stop/go operation. During this time, there will be no right turn into Cobden Street from Karangahape Road, but vehicles exiting Cobden Street can turn either left or right at all times.

Edinburgh Street to Gundry Street

Upcoming works - what to expect: 

  • Commence with ducting and kerbline construction
  • Prepare for raingarden construction

Gundry Street to Newton Road

Upcoming works - what to expect: 

  • Commence with preparation for new services installation
  • Commence with kerbline preparation
 
 

Photo:  Heritage kerbs carefully removed for reuse

 

Upcoming section - Overbridge to Pitt Street:

The section between the Overbridge and Pitt Street is expected to commence end of November 2020, pending traffic management approval.

Change in temporary traffic management - Day Street

In order for the speed table to be constructed, Day Street intersection with Karangahape Road will be closed for approximately two weeks in early December.  Access to Day Street will be via Hopetoun Street only during these works.  Footpath access along Karangahape Road will be maintained around our works. 

 

Service trenches across carriageway: 

Part of the upgrade includes traffic lights, street lights and future proofing ducting, and stormwater connections across the carriageway of Karangahape Road.  The enabling works are complete and the trenches commence this week.  These works require sections of Karangahape Road to be closed, with detours in place for vehicles.

Upcoming night works - what to expect:

Commence service trenches at:

  • Queen Street and Karangahape Road intersection
  • The mid-block pedestrian crossing, between Queen Street and Pitt Street

Works continue up to 23 November 2020  from 19:30 - 06:00. 

These works will be undertaken at night when traffic volumes are low. A change in lane layout will be required while this work is taking place, however vehicle and footpath access will be maintained around the work.

Please note there will be intermittent medium to high volume noise - saw cutting, excavation, trucks and diggers moving and loading heavy equipment.

 

Upcoming works - Asphalt Resurfacing:  Pitt Street to Symonds Street

Final resurfacing of the road is part of the completion of the enhancement work currently being undertaken. 

The resurfacing work is being split into several phases: the section between Pitt Street and Queen Street is the first phase, and Queen Street to Symonds Street is the second phase.  The remaining section from Pitt Street to Ponsonby Road will be done near the end of the enhancement project.

This resurfacing process is known as "mill and fill".  The existing asphalt surface is "milled" off to achieve an even surface, removes old trench marks  and "ghost" road-markings.  This is then replaced with a new asphalt layer (fill) on the entire width of the road.  Once this is complete the final road markings will be done.  

Heavy machinery is used to do this work.  It is anticipated that this work will be completed over a couple of weeks.

These works require sections of Karangahape Road to be closed, with detours in place for vehicles. Karangahape Road is a main arterial route during the day and therefore these works will be undertaken at night when traffic volumes are low. Every morning works will be finished in sections to ensure there is a trafficable surface during the day.

During the day on street parking will be removed daily on the hours prior to the works commencement to enable the machine access.

It is important to note that vehicle and pedestrian access will be maintained at all times during the day.

This work is expected to commence in November and will take a few nights to complete - the details will be shared in upcoming newsletters.

Information about AT and how their roadworks may impact can be found on the AT website

 

STAGING & LOADING ZONES 

Parking and Loading zones:

Below is a map of the Karangahape Road precinct showing the construction stages, temporary bus stop relocations and loading zones.

Auckland Transport’s parking enforcement is working to ensure parking is being correctly used throughout the Karangahape Road precinct.  If you have a request for parking enforcement, please call Auckland Council on 09 301 0101.

Loading zone map below 

 

If you have any construction queries during the project, we encourage you to contact us on 
0800 KRD JFC (0800 573 532) or karangahaperoad@jfcltd.co.nz

 

If you know of anyone who would like to receive these updates, feel free to forward this email to them and get them to subscribe via the link below. Or email us at karangahaperoad@jfcltd.co.nz 