JFC Construction Update - Construction Progress - Issue 43 - 22 June 2020

 

CONSTRUCTION UPDATE

Read our construction update to see what has been achieved and what is coming up on the Karangahape Road Enhancements project. 

 

Symonds Street to Queen Street

Upcoming works - what to expect:

  • Continue with underground services installation and drainage in the section between Liverpool Street and Queen Street

  • Continue with kerb stone and cycle lane kerb installation between Liverpool Street and Queen Street

  • Commence construction of the traffic island build out 

 

Upper Queen Street to Mercury Lane

We have completed the paving and new kerbline at the Upper Queen Street corner.  

Upcoming works - what to expect:

  • Complete cycleway asphalt at the Upper Queen Street corner
  • Finalise traffic island build out
  • Finalise tactiles and join the kerblines
  • Install steelwork in rain gardens
  • Commence preperation for low level planting in rain garden

Upcoming night works what to expect: 

Night works are expected to take place from Wednesday 24 June at the Upper Queen Street corner to move the existing traffic light.

These night works are taking place in the evening due to lower pedestrian and vehicle numbers as changes to traffic management are required.  To do this safely there will be changes to vehicle and pedestrian access during these works and diversions will be in place.

Works include moving the existing traffic light to a temporary drum so that work on the kerbline can continue, and relocating existing infrastructure out of the carriageway. This work is expected to take three nights to complete, starting from 19:30 to 04:30 each night.  

Please note there will be intermittent medium to high volume noise, i.e. grinding but we will endeavour to have noisy works completed by 10:30pm

 

Mercury Lane to West Terrace

Upcoming works - what to expect:

  • Commence dig out of rain garden near the Mercury Lane corner
  • Continue construction in the carriageway and the outer edge of the footpath
  • Continue with rain garden installation
  • Continue with stormwater drainage upgrade and installation of new ducting
  • Continue laying cycleway and kerbline

Temporary Traffic management change - East Street:

When we return in late June to construct the speed table there will be a change to the temporary traffic management

West Terrace temporary road closure - planned start end June:

Work to construct the speed table in West Terrace is planned to start end-June, subject to traffic management approval.  Due to the narrow nature of West Terrace, a temporary road closure is required to construct the speed table. There will be no access to West Terrace via Karangahape Road. 

Vehicle access will be provided to residents only via Galatos Street. 

Pedestrian access from Karangahape Road to West Terrace will be unavailable during working hours. However, in the evenings, we will reduce our working space/fencing and make pedestrian access available.

During the day pedestrian access to Karangahape Road from West Terrace will be via East Street and Galatos Street.  This work is expected to take 6 weeks.

 

Overbridge

The steel work for the overbridge has been delivered and installation has commenced.  Coloured surfacing of the cycleway on both sides of the overbridge has also commenced with an additional treatments to be completed over a two week period

Upcoming works - what to expect: 

  • Continue to install fabricated bus shelters on overbridge 
  • Install lights on the completed shelters on the Northern Side

Photo: Steel work installation and coloured cycleway surfacing under action

 

Hereford Street to Howe Street

The traffic management plans allow for work on one side of Howe Street at a time.  We have exposed the existing services and have also commenced installation of new ducting in this location.  

Upcoming works - what to expect: 

  • Continue relocation of services by asset owners at this location this week

Photo: Existing services exposed

 

Cycleway - "SOFT OPENING:

During the works, sections of the newly constructed cycleway have remained closed for safety reasons as they did not link up along the street. However, as works are progressing we can facilitate a soft opening of the cycleway now instead of opening it fully at the end of the project.  In conjunction with AT and Bike Auckland we are opening sections of the cycleway - there will be temporary signage and road markings to help guide cyclists on along the cycleway.  Please follow these signs and dismount when required

While this "soft opening" will allow cyclists to utilise sections of the cycleway that do not have active construction in them, it is important to note that construction work will take place later at some of these ‘open’ cycleway sections to finalise construction.     

In these instances, we will have the relevant traffic management in place to indicate these work locations but we will endeavour to maintain cycleway access.

Temporary road markings are completed on the eve of the opening.

The following are planned sections to be opened - dates will be confirmed in the upcoming newsletters:

Ponsonby to Hereford Street:  Wednesday 24 June 9am

Hereford Street to Howe Street (Dismount before Howe Street): TBC

Upper Queen Street to Mercury Lane:  TBC

Overbridge North Side: TBC

Overbridge South Side: TBC

Photo: Cycleway signage

 

STAGING & LOADING ZONES 

Upcoming section: 

The section between Queen Street and Pitt Street commences after the section between Symonds Street and Queen Street is complete.  This section is expected to commence mid to late July.

Parking and Loading zones: 

Below is a map of the Karangahape Road precinct showing the construction stages, temporary bus stop relocations and loading zones.

Auckland Transport’s parking enforcement is working to ensure parking is being correctly used throughout the Karangahape Road precinct.  If you have a request for parking enforcement, please call Auckland Council on 09 301 0101.

Loading zone map below 

 

If you have any construction queries during the project, we encourage you to contact us on 
0800 KRD JFC (0800 573 532) or karangahaperoad@jfcltd.co.nz

 

If you know of anyone who would like to receive these updates, feel free to forward this email to them and get them to subscribe via the link below. Or email us at karangahaperoad@jfcltd.co.nz 

Subscribe
 
Unsubscribe