JFC Construction Update - Construction Progress - Issue 32a - 3 March 2020

 

CONSTRUCTION UPDATE

Read our construction update to see what has been achieved and what is coming up on the Karangahape Road Enhancements project. 

 

    Howe Street 

    These night works are taking place in the evening due to high pedestrian and vehicle numbers as changes to the traffic management is required.  Vehicle and footpath access will be maintained around the work.  The work will alternate between the two corners over the three nights.

    Upcoming night works Howe Street eastern corner - what to expect:

    • Tonight, Tuesday 3 March 2020 outside the Thirsty Dog, night work will start for drainage and to tie into the existing water supply for the water fountain.  This work will take place over three nights but hydro excavation and breakout work will be complete by 22:30 at night, each night

    Upcoming night works Howe Street western corner - what to expect:

    • Tonight, Tuesday 3 March 2020 by Spacers, night work will start on ducting.  This work will take place over three nights but hydro excavation and breakout work will be complete by 22:30 at night, each night

    •  

      On Sunday night the existing traffic light will be removed and put into a drum so that work on the kerbline can continue

     

    If you have any construction queries during the project, we encourage you to contact us on 
    0800 KRD JFC (0800 573 532) or karangahaperoad@jfcltd.co.nz

     

    If you know of anyone who would like to receive these updates, feel free to forward this email to them and get them to subscribe via the link below. Or email us at karangahaperoad@jfcltd.co.nz 