JFC Construction Update - Construction Progress - Issue 25 - 23 January 2020

 

CONSTRUCTION UPDATE

Read our construction update to see upcoming night works on the Karangahape Road Enhancements project. Please note the teams will be working through this Monday's public holiday.

 

Ponsonby Road to Hereford Street

Upcoming night works:

  • New kerbline and footpath preparation on the corner of Hereford Street from 6pm on Thursday 23 January 2020.Works are expected to take 2 nights.
    • These works are being undertaken at night to minimise the impact on traffic access in this area.

Hereford Street to Howe Street

Upcoming night works:

  • The installation of new catchpits and ducting on the corners of Howe Street will commence from 6pm on Thursday 23 January 2020. Works are expected to take 2 nights.
    • These works are being undertaken at night to minimise the impact on traffic access in this area.

Howe Street to Overbridge 

Upcoming works - what to expect:

  • On Monday 27th January, the removal of the existing concrete footpath from the Thirsty Dog towards the overbridge will commence. This works may continue as a night shift if required, as pouring the first section of new concrete footpath is scheduled for Tuesday 28th January.
    • We will ensure access remains to businesses during concrete pours
 

If you have any construction queries during the project, we encourage you to contact us on 
0800 KRD JFC (0800 573 532) or karangahaperoad@jfcltd.co.nz

 