JFC Construction Update - Construction Progress - Issue 35 - 24 April 2020

 

Karangahape Road under alert level 3

We hope you are doing well during this time. As you will be aware, the Karangahape Road Enhancement Project has been safely closed for the duration of the level 4 alert period. 

We would now like to provide an update following on from the Government announcement that New Zealand will move into level 3 from Tuesday 28 April 2020. 

Auckland Transport and JFC has used the time in COVID-19 alert level 4 to plan the return to work with a safety focused approach.

We plan to resume work from Tuesday 28 April 2020 in construction areas detailed below.

Although our aim is to return to work as quickly as possible to minimise delays, our priority will be to ensure the safety of our workers and the general public. As such, the pace of work under alert level 3 may not be as rapid as it is under normal circumstances.

 

Health and safety and physical distancing

We would like to assure you that our teams will be following strict health, safety and physical distancing guidelines. This is to ensure the safety of our staff and the community.  Each project site has developed a Health and Safety Plan based on Ministry of Health Guidance and industry best practice.  At level 3 these measures include:

  • Physical distancing, compulsory PPE, hygiene practices on site entry and exit and separating teams into zones on our larger sites
  • There will be a full re-mobilisation and on-boarding process for each site covering COVID 19 restrictions, ensuring a staged, safe return to the projects
  • Inductions for new project staff and compulsory COVID 19 education and training will be part of ongoing site protocols whilst in a level 2 and 3 scenarios
 

Assisting businesses during alert level 3 and what we need from 

We understand that the change in how we all operate in these unusual times will be a key factor in keeping businesses going. 

We have worked with AT to accommodate temporary parking in non traditional parking spaces for collection of goods.  The plan below shows where these pick up points are along Karangahape Road, and can be shared with your customers. These parking spaces are to be shared by all businesses, and are not to be used as long term parking.

For now parking in AT’s Upper Queen Street building continues to be free with no time restrictions.

Please see the temporary parking locations indicated below:  

Please look out for these signs which will be going up early next week: 

We would like to help accommodate Karangahape Road businesses in the new norm of operations where we can. Our Stakeholder Liaison, Mara will be liaising with businesses affected by our works to discuss individual operations under level 3.  

We also encourage you to make contact with us this week on 0800 KRD JFC (0800 573 532) or karangahaperoad@jfcltd.co.nz about how you’re operating.

 

CONSTRUCTION UPDATE

Read our construction update to see what has been achieved and what is coming up on the Karangahape Road Enhancements project. 

 

Upper Queen Street to Mercury Lane

We will be removing a large portion of fencing in this block but will still need to have working space for our trucks to continue safe operations.  We will however remove a portion of fencing to create a temporary parking bay zone for the local business pick up zone.

Upcoming works - what to expect:

  • Continue work on the Upper Queen Street corner to remove the existing slip lane, connect the cycleway and reconstruct the new wider footpath
  • Continue to work on installing tactiles at mid way pedestrian crossing
 

Hereford to Howe Street

Upcoming works - what to expect:

At Howe Street corner

  • Continue with footpath preparation 

  • Install tactiles at pedestrian crossing

 

Howe Street to Overbridge

At Howe Street corner near Thirsty Dog

Upcoming works - what to expect:

  • Continue with rain garden installation 

  • Continue with electrical works including garden lights installation and street light installation

 

Overbridge

Overbridge - South side of Karangahape Road

Upcoming works - what to expect:

  • Removal of the bus shelters
  • Removal of the asphalt on the carriageway
    This involves a saw cut along the carriageway, before the asphalt is lifted off
 

Symonds Street to Queen Street

The demolition between Symonds Street to Liverpool street was mostly complete before level 4 shut down. We are now planning to extend the works to include the Queen Street intersection so that this side of the road can be worked on and completed at the same time - this is subject to approval. 

Upcoming works - what to expect:

  • Continue installation of underground services

  • Continue with construction of cycleway, traffic island and bus stop infrastructure

 

Mercury Lane to West Terrace

On Friday 1 May 2020, the team is expected to move (subject to approvals) into the section from Mercury Lane to West Terrace.

For most of this stage, construction is in the carriageway and the outer edge of the footpath, however there will be footpath reconstruction and construction of speed tables on the intersections of East Street and West Terrace with Karangahape Road.

 

STAGING & LOADING ZONES

Below is a map of the Karangahape Road precinct showing the construction stages, temporary bus stop relocations and loading zones.

Auckland Transport’s parking enforcement is working to ensure parking is being correctly used throughout the Karangahape Road precinct.  If you have a request for parking enforcement, please call Auckland Council on 09 301 0101.

Loading zone map below 

 

If you have any construction queries during the project, we encourage you to contact us on 
0800 KRD JFC (0800 573 532) or karangahaperoad@jfcltd.co.nz

 