Pool roof update
Update 5: 8 January 2019
We're raising the roof
We've got a VERY big crane coming on-site to raise and replace the pool roof at the Kilmore Leisure Centre this week.
This is a major milestone for the project.
Gym closed: 10, 11 and 14 January
Unfortunately, this will impact the gym area for a few days.
To protect your safety while the crane works on the area closest to reception and above the gymnasium, we'll need to close the centre.
-
Closed: Thursday 10 and Friday 11 January
-
Open: Saturday 12 and Sunday 13 January
-
Closed: Monday 14 January
What's next?
Weather permitting, this should be the last centre closure during the works. We've still got quite a bit of other work to do as part of the roof replacement. At this stage, we're on track to re-open early in term 1.
Thank you for your patience while we carry out these important works.
Regards,
Mitchell Shire Leisure Team
|