Period 13th July - 24th July 2020
H.H.Smith continue to monitor the current guidance around COVID-19 and practice a safe working environment.
Installation of the replacement windows the the South elevation of FASS is almost complete with the final trims being installed early next week.
The upper roof top-sheet installation is complete with minor finishing works scheduled for next week. Following this, the edge protection will be removed and the final insulated wall panels can be installed.
The window installation to the Lecture Theatre is progressing well and will continue over the coming weeks.
Wiring and plastering works to the toilet areas is ongoing, ready to receive fittings.
Drylining will be continued in the plant room and the installation of black timber cladding has commenced to the exterior of the building.
Pipework for radiators is being installed as part of the first-fix phase.
|