ISSUE 10

Artists' impression of future streetscape

Artist's impression of the future streetscape

You are receiving this newsletter as you have opted in to stay informed on the Willoughby Road streetscape upgrade.

Work began on Stage 2 of the Willoughby Road, Crows Nest streetscape upgrade in October 2023. This eNewletter aims to keep you informed on what is happening, when it is happening and who to speak to if you have any questions.

Upcoming works

The Willoughby Road upgrade project is quickly progressing as the main stormwater drainage works are now 100% complete. This work included new pits and pipes to drain surface stormwater into underground pipes..  Adverse weather has caused the project some minor delays but the project teams and contractors are working hard to mitigate further delays, ensuring the project stays on track.

The next key stages of the project are:

  • Footpath paving that began 11th June
  • Overhead electrical wires to be moved underground, leaving air space for future tree planting
  • Installation of new street lighting poles 50% complete by late July
  • Tree planting beginning late July
Work on Willoughby Road's Stormwater drainage upgrade

Work on Willoughby Road's Stormwater drainage upgrade

Temporary cover of Willoughby Road's Stormwater drainage upgrade

Temporary cover of Willoughby Road's Stormwater drainage upgrade

Paving on western side of Willoughby Road

Starting 11 June, the western side of Willoughby Road began footpath paving and is now 25% complete. Over the next four weeks, paving will continue in three stages and cover footpath and dining terraces around local shopfronts, weather permitting. Paving will be completed by 12 July, weather permitting.

The following will be completed and installed in 6 weeks:

  1. New Paving on Western side of Willoughby Road
  2. New street furniture and water drinking station
  3. Streetlighting installation 50% complete

Paving upgrade commenced on Clarke Street 11 June

Paving upgrade commenced on Clarke Street 11 June

Impact to businesses

We acknowledge that the next few weeks of construction will be challenging to businesses, pedestrians and residents in the area. An example of this is the loud noise generated by pavers being saw cut. Council’s project team will be monitoring works closely and mitigating the impact to businesses where possible. We recognise that the Willoughby Road upgrade project is disruptive and invite the community to continue engaging directly with Council regarding concerns at the phone numbers below or via council@northsydney.nsw.gov.au

More information

For the most up-to-date information, visit North Sydney Council's Willoughby Road upgrade page or contact Council's Engineering Project Manager on 9936 8286.

To make enquiries with Council's appointed contractors:

 

Paving upgrades on Clarke Street and Willoughby Road 13 June

Paving upgrades on Clarke Street and Willoughby Road 13 June