Barnard College Construction Update - May 5, 2016

Dear Neighbor,

Quiet work continues this week on the deconstruction of Lehman Hall as students prepare for finals and commencement season approaches.

Look-Ahead

Construction Schedule:

  • Friday, May 6 – non-noisy construction from 8 a.m. – 4:30 p.m.
  • Saturday, May 7 – non-noisy construction from 9 a.m. – 5 p.m.
  • Monday, May 9 through Thursday, May 12– non-noisy construction from 8 a.m. – 6:30 p.m.
  • Friday, May 13 – regular construction from 8 a.m. – 4:30 p.m.
  • Saturday, May 14 – non-noisy construction from 8 a.m. – 5 p.m.
  • Monday, May 16 – regular construction from 8 a.m. – 6:30 p.m.
  • Tuesday, May 17– non-noisy construction from 8 a.m. – 6:30 p.m 

Questions?

For general questions and comments, please email me at newbuilding@barnard.edu.

If you have an urgent issue that needs to be addressed immediately, please email constructionteam@barnard.edu during regular work hours, or call Barnard Public Safety at 212/854-3362 outside of regular work hours.

You can also find our overall construction plan and specific construction-related FAQs on our website: http://barnard.edu/about-barnard/new-teaching-learning-center/construction-faqs.

Thank you.

Sincerely,

Quenta Vettel, Communications Director, Special Projects
Barnard College