Barnard College Construction Update - Feb. 18, 2016

Dear Neighbor,

This has been a relatively quiet construction week on campus.  The abatement work has been completed in Lehman Hall and the construction team is preparing the building for demolition. We expect that work to begin in early March and should be finished by mid-to-late May.  This week, we also started building the scaffolding on the south side of campus between Lehman and the Barnard Hall Annex.

Here's what to expect over the next two weeks:

Two Week Look-Ahead -- Feb. 18 – March 3

In addition to preparing Lehman Hall for demolition, we also will be finishing the installation of the sound-deadening blankets inside the construction fences around the entire perimeter.  These blankets have already been installed on the inside of the two entrances to the site.

Questions?

We appreciate your consideration and patience. For general questions and comments, please email me at newbuilding@barnard.edu. If you have an urgent issue that needs to be addressed immediately, please email constructionteam@barnard.edu during regular work hours, or call Barnard Public Safety at 212/854-3362 outside of regular work hours.

You can also find our overall construction plan and specific construction-related FAQs on our website: http://barnard.edu/about-barnard/new-teaching-learning-center/construction-faqs.

Have a great rest of the week.

Sincerely,

Quenta Vettel, Communications Director, Special Projects