Barnard College Construction Update - May 12, 2016

Dear Neighbor,

A mix of regular and non-noisy deconstruction workdays continues this week – we will resume normal deconstruction activities the afternoon of Wednesday, May 18. We still expect to be finished with this phase by mid-June. 

In addition, we will not be doing noisy construction on the Saturday of Memorial Day weekend (May 28) and will not have construction activities at all on Memorial Day (Monday, May 30).

Look-Ahead

Construction Schedule (through commencement):

  • Thursday, May 12- non-noisy construction from 8 a.m. -- 6:30 p.m.
  • Friday, May 13 - regular construction from 8 a.m. -- 4:30 p.m.
  • Saturday, May 14 - non-noisy construction from 9 a.m. -- 5 p.m.
  • Monday, May 16 - regular construction from 8 a.m. -- 6:30 p.m.
  • Tuesday, May 17 (senior receptions and commencement) - non-noisy construction from 8 a.m. -- 6:30 p.m.
  • Wednesday, May 18 – non-noisy construction from 8 a.m. -- 2:30 p.m., regular construction activities after 2:30 p.m.

Questions?

For general questions and comments, please email me at newbuilding@barnard.edu.

If you have an urgent issue that needs to be addressed immediately, please email constructionteam@barnard.edu during regular work hours, or call Barnard Public Safety at 212/854-3362 outside of regular work hours.

You can also find our overall construction plan and specific construction-related FAQs on our website: http://barnard.edu/about-barnard/new-teaching-learning-center/construction-faqs.

Thank you.