No Images? Click here Barnard College Update - Tuesday, April 4, 2017Dear Claremont resident: We have made significant progress over the past week on the erection of the steel structure even with a couple of days lost due to weather. We will continue working over the next few weeks and hope to finish this phase towards the end of the month. We plan on pouring concrete for the third floor tomorrow (Wednesday, April 5) so expect an increase in traffic along Claremont as the concrete trucks come to the site. In addition, we expect the masons will be working into the evening, finishing the concrete and making certain it is level and smooth. Additional workers will remain onsite overnight to monitor the heaters that help cure the concrete. We will have tarps covering these areas that should help mask the lighting and activity, but we did want to share with you that workers will remain onsite tomorrow during the evening and overnight hours. Schedule The schedule continues to be Monday through Friday, 8 a.m. - 6:30 p.m. and Saturdays, 9 a.m. - 5:30 p.m. Questions? For general questions and comments, please email me at newbuilding@barnard.edu. If you have an urgent issue that needs to be addressed immediately, please email constructionteam@barnard.edu during regular work hours, or call Barnard Public Safety at 212/854-3362 outside of regular work hours. You can also find our overall construction plan and specific construction-related FAQs on our website: http://barnard.edu/about-barnard/new-teaching-learning-center/construction-faqs. Thank you. Sincerely, Quenta Vettel, Communications Director, Special Projects |