What happened in February
Last month work continued around the Maunganui-Girven intersection and along State Highways 2 and 29A, near Baypark.
This work included:
-
Installation of drainage under SH2 between Matapihi Road and Bayfair Shopping Centre.
-
Progressing earthworks for the new northbound on and off ramps at the Maunganui-Girven intersection and new SH29A roundabout in preparation for pavement works.
-
Removal of the median concrete barriers along SH29A.
-
Power, gas and sewer relocation works continuing along SH29A and SH2.
-
Locating and protecting underground services and continuing removal of vegetation.
A 50km/h temporary speed restriction is in place throughout the site for the duration of the project for the safety of drivers and their passengers, and also for the people working on the project. Please take care driving through the site.
The works around Harris Street and Bayfair Shopping Centre are part of the Bayfair expansion and not related to this project.
|