1. Lifting beams at Greenhill Interchange

Story
Story

The Greenhill Interchange that will link the expressway with Wairere Drive is taking shape. Beams have been placed on the interchange bridge, and the team building it is now preparing to pour the concrete deck.

This interchange will link via Pardoa Boulevard to the large roundabout where Wairere Drive meets Gordonton Road.

Story
 
Image

 
Story

2. Progress on Resolution link

Laying a rock foundation for the Resolution Extension is almost complete. Construction teams have removed most of the topsoil and replaced it with rock so the road can be built on top in the spring. Drainage teams will be back forming swales and ponds when the wet weather eases up.

At the Resolution Interchange, dump trucks are laying sand when the weather allows.

Story
 
Image

 
Story

3. Safer curves at Osborne Road Bridge

Building the Osborne Road Bridge also included a realignment of the road at either end to remove potentially dangerous S-bends. The photo below shows the new, gentler curves and barriers at either end of the completed bridge.

Story
 
Image

 
Story

4. It’s our longest…

The bridge we’re building over the Mangaonua Gully is our longest at 150 metres. Bored piles extend 50 metres into the soft gully soils, and we’re now building the first centre columns. This is the only bridge on the project with steel beams.

Story
 
Image

 
Story

5. Roundabout taking shape

The new roundabout at the intersection of SH26-Morrinsville Road and Ruakura Road is now sealed. This large roundabout is constructed from multiple layers of bitumen laid 180mm deep to resist the pressures of heavy, turning vehicles. More bitumen is coming for the roundabout approaches, and then Ruakura Road will be finished and sealed through to Vaile Road.

Story
 
Image

 
Story

6. Running trucks in winter is a balancing act

In the height of summer, we have 40 or more 6WD dump trucks hauling sand and soil up and down the expressway construction corridor. This winter, we have approval to push on with earthworks, but the weather dictates how much we can achieve.

Story
 
Image

 
spacer

More information

spacer
 
 
Story

For more information on the Hamilton section of the Waikato Expressway, contact us at waikatoexpressway@nzta.govt.nz or phone us on 0800 322 044.

Visit our website www.nzta.govt.nz/hamilton

Story