Welcome to the Construction Update for the Baypark to Bayfair link upgrade project.

CPB Contractors will be carrying out the design and construction of the project and we look forward to bringing you these monthly updates, which provide an overview of what's happened, and what's coming up for the project.

Construction updates will be provided in the months between the NZ Transport Agency's quarterly project newsletter. The next quarterly newsletter will be out in October 2017.

Story
 
Image

Image
Story

Secure temporary fencing is being installed as the site is being prepared for the start of construction. Photo top right - establishment of the site office is underway.

Story
 
Story

What's happened in July

During July, enabling works began to prepare the site for construction. This involved carrying out survey and ground investigation work, removal of fencing and installing temporary fencing. Development of the detailed design continued.

Work included:

  • Surveying and ground investigation in the shoulders to verify the location of existing utility services. Services such as power, gas and telecommunications need to be re-located before physical works can begin. Discussions with priority utility service providers are underway to confirm the design for these relocations.

  • The removal of existing fencing and installation of secure temporary fencing along the Owens Place property boundary started.

  • Development of the detailed design is about 50% completed and is on track to be finished by the end of 2017.

Story
 

Image
Story

As part of the enabling works, hydro vacuum excavation is being used to locate utility services. Relocating these services will be one of the first tasks when construction begins.

Story
 
Story

What to expect during August

August will focus on completing the enabling works and beginning the relocation of utility services.

Work this month includes:

  • Completion of the ground investigation and survey work in early August.

  • Finishing the removal of existing fencing and installation of secure temporary fencing along the Owens Place property boundaries.

  • Site office establishment in Titoki Place, involving preparation for service connections and installation of portacom buildings.

  • Moving utilities before construction begins is the best way to avoid service disruptions to customers. At the end of August the relocation of fibre optic cables will commence. New ducts will be installed in the northbound shoulder close to the boundary to ensure services are clear of ground that pavements will be built on.

Story
 

 
Story

You'll be seeing works starting to ramp up from mid-September and see our team on the ground. We're aware of the complexities of this project and if you ever have any questions or queries please don't hesitate to contact us on 0508 222 3646 (0508 B2B INFO) or by using the details below.

Thank you for your patience as we work to improve journey reliability and safety between Baypark and Bayfair on State Highway 2 / State Highway 29A.

Story
     

 
spacer

More information

spacer
 
 
Story

For more information on the Baypark to Bayfair link upgrade project, contact us Baypark2Bayfair@nzta.govt.nz

Visit our website www.nzta.govt.nz/b2b