Week commencing 28 October 2018

Intended programme for next week (weather dependent, therefore subject to change)

SH2 & SH29A
Right lane closures will be initiated while the Te Maunga and Baypark splitter islands and roundabouts are removed and replaced with a temporary alternative. Minimal traffic delays are expected. Sunday 28 October to Thursday 1 November 2018. Nights: 7pm to 6am.

Owens Place  A contra flow remains in place during service relocation works in the verge next to HomeZone. Minimal traffic delays are expected. Sunday 28 October to Saturday 3 November 2018. Nights & days: ongoing.

SH2 - northbound Truck and trailer movements through Site Access Points 3, 4 and 6 to deliver pumice, sand and aggregate for roading and stone columns. Minimal traffic delays are expected. Monday 29 October to Friday 2 November 2018. Days: 9am to 4pm.

SH29A - eastbound Semi statics will be deployed while installing ground improvements next to the existing road. Minimal traffic delays are expected. Monday 29 October and Tuesday 30 October 2018. Days: 9am to 4pm.

Long-term traffic management
• State Highway 2 between Te Maunga roundabout and Concord Avenue - narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.

• Matapihi Road, adjacent to the golf driving range – narrowed lanes and a 30km/h temporary speed restriction is in place for the duration of the project.

• Girven Road, near the Bayfair roundabout - narrowed lanes are in place for the duration of the project and the right-turn from the Bayfair Shopping Centre car park onto Girven Road is permanently closed.

• Access onto State Highway 2 / Maunganui Road from Exeter Street is closed for approximately 18 months.

• SH29A near Baypark – narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.

Advanced notice of significant works

SH2 & SH29A Right lane closures will be initiated while the Te Maunga and Baypark splitter islands and roundabouts are removed and replaced with a temporary alternative. Minimal traffic delays are expected. Sunday 4 November to Thursday 8 November 2018.. Nights: 7pm to 6am.

Matapihi Road Lane closure required between Maunganui-Girven intersection and the rail crossing to install a water main pipe. This section of road will be reduced to one lane and managed by temporary traffic signals. Traffic delays are expected. Sunday 4 November and Monday 5 November 2018.
Nights: 7pm to 6am.

Matapihi Road A contra flow will be in place between Owens Place and the rail crossing during installation of kerb and channel near Home Zone. Minimal traffic delays are expected. Tuesday 6 November to Thursday 8 November 2018. Nights: 7pm to 6am.

SH29A Closure of SH29A between the Te Maunga and Baypark roundabouts to install stone columns, and install barriers and new line marking. Sign posted detour will be in place. Traffic delays are expected. Friday 9 November to Monday 12 November 2018. Nights & days: 9pm Friday to 4am Monday.

Matapihi Road & Owens Place Contra flow in place during excavation of test pits near Home Zone.Minimal traffic delays are expected. Sunday 11 November and Monday 12 November 2018.Nights: 7pm to 6am.

SH2 - TEL Northbound lane closure required while barriers are placed near the Te Maunga intersection to establish a new work area. Sunday 11 November to Wednesday 14 November 2018. Nights: 7pm to 6am.

SH29A Closure of SH29A between the Te Maunga and Baypark roundabouts to install stone columns. Sign posted detour will be in place. Traffic delays are expected. Friday 23 November to Monday 26 November 2018. Nights & days: 9pm Friday to 4am Monday.