Works around Bayfair this week
If you have been through the Bayfair area you will have seen a lot of road cones around.
We are doing night works this week and next to start establishing the site boundaries. This involves removing some kerbing and central islands, changing line marking and installing barriers which will narrow the lane widths, and next week we will be lowering the speed limit through the area to 50km/h.
Our traffic report is online and is updated weekly: www.nzta.govt.nz/projects/baypark-to-bayfair-link/traffic-notices/
Bayfair Shopping Centre is also carrying out infrastructure improvements, such as upgrading the storm-water facilities. This work is not part of the Bay Link project, however the project team is working closely with the Bayfair Management Team. On the local roads, Harris Street access at the Bayfair end will be closed for the duration of these works.
|