5 October 2018

We wish to advise that there has been a delay to the earlier publicised lane switching affecting traffic on Main South Road (between Hoskyns Road and Robinsons Road). It is now programmed for early November.

The reasons for this is that we have decided to carry out additional work before making the switch, including constructing the final pavement under the bridge, thereby removing the need for an additional traffic switch in future.

Work was able to occur elsewhere along the corridor instead and the delay has been accounted for within the overall programme

Story
 

 
spacer

More information

spacer
 
 
Story

For more information on the Christchurch Southern Motorway – Stage 2 project, visit our website www.nzta.govt.nz/CSM2