2021-24 NLTP development
-
This week we held the initial moderation sessions for improvements and low cost low risk activities; the final moderation of continuous programmes will occur later in the month.
-
We expect to provide feedback to councils by mid-March, after these sessions have finished.
-
Thank you for completing the detail needed for new activity management plans and continuous programmes templates.
-
This additional information, for example on benefits and RLTP alignment, will support improved reporting of expenditure against outcomes for the GPS and RLTP objectives.
-
We're currently working on the details for the improvement templates, including low cost low risk, and expect to have these available within the next month.
-
We’ve also recently updated TIO so you can now archive any activity that is not funded and not submitted for inclusion in the 2021-24 NLTP.
-
Before the release of the improvements and low cost low risk templates, we're asking you to move all activities that are no longer required to the archived activities list. Further information on how to archive phases can be found on the TIO homepage.
-
We're in the process of responding to your submissions on the Waka Kotahi Investment Proposal. Once all replies are sent, we will share any changes made to projects in the regions.
-
The feedback we received on the proposed non-state highway activities will help inform which activities are prioritised for inclusion. The activities will be assessed and prioritised in the coming months, before a final list is developed and put forward for approval.
|
|
|
|