Measure B NewsletterThis newsletter is to help inform our Marin Community College District community of the District’s progress on the implementation of the voter‐approved Measure B bond. The improvements made possible by this bond allow us to continue our commitment to educational excellence in providing equitable opportunities and fostering success for all members of our diverse community.
Resolution No. 2020-05 Designating Essential Function Public Works Projects
- The Health Officer of the Marin County Department of Health Services issued a "stay at home" Order 20-04 on March 31, 2020, which placed additional restrictions on Construction Projects.
- Having received that order, District staff evaluated the list of Measure B projects and prepared an analysis for all projects and reviewed with legal counsel and senior staff.
- Letter from the Superintendent/President was sent to contractors on April 6, 2020 which provides a list of projects that could continue as "essential government functions".
- A Board Resolution (No. 2020-05) was prepared to ratify this initial determination.
Bolinas Marine Laboratory
Status Update: - Submitted project for County of Marin Planning Review on December 13, 2019
- Received initial Planning Department review comments on January 10, 2020
- Community EIR and Project follow up meeting held on March 2, 2020
- Geotechnical preliminary report in process to meet Planning request
- Architectural Historian report in process to meet Planning request
- Resubmission to County of Marin Planning Department estimated to be by May 25, 2020
New Learning Resources Center Building | Kentfield Campus
Project Summary: Demolition of existing and construction of new Learning Resource Center building Status: - Architect transitioning from the programming/planning phase to the conceptual design phase
- A community input survey was distributed to gather responses from the community. The District is planning to host an in-person town hall meeting once the stay-at-home order is lifted.
- District Staff evaluating building estimates and have given direction to architect which has resulted in a max building size of 85,000 gross square feet (GSF)
- Exterior Abatement & Demolition expected Summer 2020
- Anticipated DSA submittal for new building by March 2021
Environmental Impact Report (EIR) Meetings: - District conducted 6 EIR meetings prior to publication of the Draft EIR (4 onsite meetings & 2 Zoom meetings)
- Consultant incorporated the questions and provided responses to the comments received by the public and California Department of Fish & Wildlife
- Draft EIR is out for review with the 45-day review period starting on April 3, 2020 and review ending on
May 18, 2020
- Tentative schedule for EIR Certification by the Board of Trustees is scheduled for the June 16, 2020 Board meeting
Admin Cluster - Building 12 Renovation | Indian Valley Campus
Project Summary: Renovation to create café and student spaces Status: - Occupants have vacated
- Abatement work complete
- Interior demolition complete
- Interior design in
review
- Further site and/or related demolition work put on hold due to latest stay at home order
Projects currently under construction:
Jonas Center and Building 18 | Indian Valley Campus
Project Summary: Event facility to seat 300 people, includes a catering kitchen, a prep kitchen, stage and meeting rooms Status: - Interior finishes and exterior stucco ongoing through May 2020
- Hardscape and paving will progress through June 2020
- Testing and punch list will proceed through July 2020
- Project proceeding
with restrictions per Resolution authorizing certain Measure B projects to proceed under new stay at home order
New Miwok Center - Aquatic & Fitness Center | Indian Valley Campus
Project Summary: Construction of a multi-purpose aquatic fitness facility, with flexible work-out spaces, dance studio, classroom, locker rooms, and offices Status: - Underground water, gas, storm drain and electrical utility installation in April - May 2020
- Drill and place dive tower piers in April - May 2020
- Structural steel columns and beams in May - June 2020
- Further site work put on hold
Maintenance & Operations Building and District Warehouse | Kentfield Campus
Project Summary: District Warehouse and Facilities Administration Building Status: - Punch list (storage building and admin building interior finishes) in May 2020
- Landscaping and paving scheduled for May 2020
- Adjacent site work and fire lane in Summer 2020
- Project proceeding per Resolution authorizing certain Measure B projects to proceed under new stay at home order
Fusselman Hall: Structural and Waterproofing Improvements | Kentfield Campus
Project Summary: Structural and waterproofing improvements Status: - Interior finishes will be complete in May 2020
- Exterior landscaping and punch list in June 2020
- Project proceeding per Resolution authorizing certain Measure B projects to proceed under new stay at home order
Learning Resources Center (LRC): Temporary Campus Bookstore | Kentfield Campus
Project Summary: Renovation of existing Maintenance & Operations building for use as the temporary campus bookstore during demolition of the LRC Status: - Interior finishes completed in April 2020
- Store relocated to new space in April 2020
- Project proceeding per Resolution
authorizing certain Measure B projects to proceed under new stay at home order
Projects bidding Spring/Summer 2020:
Learning Resources Center: - Stormwater Pollution Prevention Plan (SWPPP) Consultant | Kentfield Campus
- Lease-Leaseback Request for Proposal Expected to be released in June 2020
For any questions or comments regarding current or future projects, please contact: Isidro Farias