Welcome to the latest edition of the North Sydney Olympic Pool (NSOP) e-newsletter

Our monthly updates will help keep you informed on the pool redevelopment progress, key milestones, and details about our upcoming state-of-the-art community facility, as we move towards the final stages of construction. 

 
 

Project update

Council’s contractor, ICON, is now reporting that the pool construction will be complete by May 2025 due to delays with the structural steel for the 25m indoor pool roof, which is currently in dispute. Council’s priority remains on delivering a first-class facility that meets the needs of the community, and we will continue to keep you updated. 

Progress this month includes the recent commissioning of the electricity substation to provide permanent power to the site, which marks a significant milestone on the project. The commencement of zinc cladding installation on Level 4 has also begun, and the high-level services on Level 3 of the facility and the new Level 2 gym area are now complete. Tiling of the walls adjacent to the 50m pool has also now commenced and internal waterproofing and wall tiling continues on Level 1. 

For all the latest information, please see the Council Meeting Report - Monday 9 December 2024. 

This month we also have a video update hosted by our Manager, Leisure and Aquatics, Duncan Rennie, focused on the progress of the 50m pool: 

 
 

We hope you’re finding our North Sydney Olympic Pool e-newsletter informative and look forward to keeping you updated with future editions. 

For all the latest updates, please visit Council’s website.

North Sydney Olympic Pool redevelopment – North Sydney Council (nsw.gov.au)

 

 
FacebookInstagramLinkedInWebsite
 
 

North Sydney Council
200 Miller Street
North Sydney 2060
Telephone: (02) 9936 8100

You are receiving this e-newsletter because you subscribed to North Sydney Olympic Pool e-News

Preferences  |  Unsubscribe