Major concrete pours set to begin + latest drone footage of the site

Christchurch City Council
Update
 
Drone image of construction of Te Kaha

Major concrete pours for Te Kaha to begin later this month

Work on Te Kaha, Canterbury’s Multi-Use Arena, will hit a new milestone later this month when the first of the foundations’ major concrete pours is completed.

Te Kaha Project Delivery chief executive David Kennedy, says the lead contractor, BESIX Watpac, will oversee about 40 large concrete pours between 27 January and mid-August, as work begins on the arena’s substructure.

“These concrete pours are significant as they signal the start of the main construction of Te Kaha,” says Mr Kennedy.

Read more

Latest site camera image and drone footage

Te Kaharoa site overview photo.

Above is a photo that was taken of the Te Kaha site from BESIX Watpac's offices this week. You can see the steel framework of the arena's southwest corner substructure (foundations and underground supports) beginning to take shape, in advance of the first major concrete pour later this month.

The large 300-tonne capacity crawler crane in the middle of the shot takes care of all the heavy lifting. It is currently helping install the reinforcing, and will also be used to lift the concrete formwork and structural steel later in the project.

In the drone footage below (taken yesterday 12 January) you can also see the ground improvement works continuing to progress across the site. The three rigs are now working on the northern and eastern stands, with this part of the project now past the halfway mark.

Drone footage of the Te Kaha site construction
 
Detailed Design artist impression of Te Kaha

What to expect over the coming months

The next six months of the Te Kaha project will be mainly focused on completing the ground improvement work and progressing the arena's substructure (foundations and underground supports), then commence on the superstructure bowl.

Because of the huge size of the project, the different stages will overlap to streamline the process. That means as one phase of work progresses across the site (working from south to north), the next phase will follow closely behind it.

Q1 2023 - Ground improvement continues.

Q1-Q4 2022 - Work continues on Te Kaha's substructure.

Q1 2023 - Construction begins on superstructure bowl.

 
 
Christchurch City Council Facebook
 
Christchurch City Council Twitter
 

You received this email because you are subscribed to receive updates from Christchurch City Council. 
If this has been forwarded to you, and you wish to receive future updates, you can subscribe here.
Privacy policy.

 
 
Christchurch City Council
53 Hereford St, Christchurch Central City, Christchurch 8013
Preferences  |  Unsubscribe