Progress, access and safety

Mordialloc Creek entrance

Community Update 
Mordialloc Creek Sheet Pile Wall Replacement

October 2022

 

In partnership with the Department of Environment, Land, Water and Planning (DELWP) we’re replacing the sheet pile wall at Mordialloc Creek. Once complete, the new sheet pile wall will help to prevent erosion and support the existing wave baffle structure along the creek entrance. The new sheet pile wall is designed to be durable and resilient.

 

What we're doing

The entrance to Mordialloc Creek is lined with wave baffle structures, designed to reduce the wave action within the creek. These extend for approximately 100 metres on both sides of the entrance. Originally built in the 1990s, replacement wave baffles were installed in 2017 in front of the sheet pile walls. Repairs to the sheet pile walls were also undertaken at this time including pouring concrete behind the walls to close holes. Despite these repairs, recent inspections revealed rapid deterioration of the infrastructure.

Working with consultants Cardno Pty Ltd, we have assessed the current condition of the creek wall infrastructure and factored in future sea level rise to determine a recommended approach to mitigate wave impacts at the entrance to Mordialloc Creek.

Following this assessment, in March 2022 we commenced construction of new coastal infrastructure to help reduce the natural impacts of coastal erosion, while ensuring safe boating access is retained in the creek.

This includes replacement of a 175-metre section on the southern side of the creek entrance which is now complete and a 140-metre section of the sheet pile wall on the northern side.

 

Making progress

On ground works on the southern side kicked off in March 2022 and after months of challenging weather conditions, works on this side of the creek are now complete.

The next step has been to establish a works compound on the northern side of the creek, near the entrance to Mordialloc Pier to allow works on the northern section to begin.

The project was due for completion late 2022 but as a result of challenging storm and tidal conditions during winter 2022, the project is now anticipated to conclude in autumn 2023.

 
Works in progress at Mordialloc Creek
Mordialloc Creek wave baffle detail
 

Project timeline

  • Planning and approvals: April - December 2021 completed
  • Tender for construction: September - October 2021 completed
  • Works commence: March 2022

           Works on South side of Mordialloc Creek completed

           Works on North side of Mordialloc Creek current

  • Works conclude: Autumn 2023
 
Work area plan

Image – map showing access when visiting Mordialloc Creek and Mordialloc Pier.

 

Enjoying the area safely

Please respect fenced closure areas and follow on-site signage directions. These closed areas are in place to keep visitors safe when visiting the area. The works are relatively non-intrusive, however if you’re visiting the site during normal construction hours, you may experience noise and slight vibrations.

Construction impacts and closures

We’re seeking to minimise impacts and inconvenience where possible and appreciate your patience as we deliver this important project.

While works are underway please be aware of the following:

Carparking - expect some reduced carpark access to the pier end of Pier Road during the next stage of works as a portion of this area is required for the construction compound, this will affect approximately 20 carparks which will be unavailable.

Fishing access – there’s currently no access to the catwalk (wave baffle) on the northern side of Mordialloc Creek. Fishers can access and use the northern side of Mordialloc Pier but should pull lines in as vessels approach.

Pedestrian access – there’s no access available to the boardwalk along the northern side of Mordialloc Creek entrance. Pedestrians can access Mordialloc Pier using an alternative path from the carpark. Mordialloc Pier, the foreshore trail and creek side trail remain open.

 
Mordialloc Creek
Facebook

Stay up to date

Further information is available at parks.vic.gov.au/projects or by subscribing for email updates. 

Subscribe
 
 

Parks Victoria, Level 10, 535 Bourke St, Melbourne VIC 3000 Australia
Contact 13 19 63, engage@parks.vic.gov.au

This email is sent from Parks Victoria via Campaign Monitor. You are receiving it as you've been identified as a key stakeholder or you've opted in to hear from Parks Victoria. View Parks Victoria's privacy policy at parks.vic.gov.au/privacy 

Unsubscribe