As we enter the second half of 2024, we want to provide an update on our efforts to deliver repairs to Flinders Pier while ensuring we preserve its heritage values.

Last year we successfully completed updates to the Flinders Foreshore Conservation Management Plan in collaboration with Mornington Peninsula Shire Council. This plan serves as a document to guide our conservation efforts and ensure any works are in line with heritage preservation principles. 

Following the completion of the Conservation Management Plan, we have prepared an Options Report to examine various approaches to the repair works, ensuring they offer the best value for money. This includes detailed proposals for different repair packages, considering both financial and structural feasibility.

Since our last update, a Heritage Consultant has been engaged to undertake technical studies and assessments and prepare a comprehensive Heritage Impact Assessment. This critical assessment involves gathering detailed marine archaeological information from beneath the pier and conducting extensive marine ecological studies. These evaluations are essential to understand the potential impacts of the repair works on the pier's historical and ecological context. 

Once completed, this assessment will support our permit application under the Heritage Act and enable a determination on the most feasible repair option. 

 
Flinders Pier
 

Planning phase 

Subject to on-ground and industry conditions and heritage conditions, the timeline for the planning phase is estimated below:
•    Planning and initial procurement of technical consultants - Complete
•    Update to the Conservation Management Plan with Mornington Peninsula Shire Council – Complete
•    Options Report (with proposed packages for repair works) - Complete
•    Costs evaluation on Options Report (and recommendation for repair works scope) – Mid 2024
•    Heritage Impact Assessment (on Options Report) and Heritage Act permit application – Underway
•    Marine ecology and archaeology evaluation on Options Report (and proposed repair works) – Underway
•    Submit permit application to Heritage Victoria for repairs to Flinders Pier
•    Heritage Victoria permit for approved project scope for repairs

Delivery phase* 

•    Contractor procurement 
•    Commencement of repairs 
•    Repairs completed 
* Commencement of delivery phase is dependent on the completion of the planning phase. 

 

Learn more about the Flinders Pier project

 
 
Find out more
 
 

Parks Victoria, Level 10, 535 Bourke St,
Melbourne VIC 3000 Australia,
Phone 13 1963

This email is being distributed using Campaign Monitor, you can read their privacy policy here.

 
Department of Transport and Planning
Parks Victoria Website
 
 
Unsubscribe