Trickling filter work hits the halfway markOur contractors removing the material from inside the first trickling filter have all but completed the job, before they start work on the second trickling filter next week. The above drone video was taken on Wednesday, which shows the two 20-tonne excavators scraping together the remaining pieces of material and concrete. The second ramp has been completed so that the contractors can begin removing the material from the second trickling filter next week. The chipper and compactor are also being relocated so that everything is in place for next week’s work. No long-term harm expected from wastewater
|