No images? Click here Gipps Street Elevated PathCommunity Update | August 2025 Welcome to the latest community update for the Gipps Street Elevated Path Project, a significant initiative aimed at enhancing accessibility and connectivity along the Main Yarra Trail. ![]() New sections of the ramp recently installed on site. Project statusParks Victoria is on track to complete this project by December 2025. Works recently completedIn August we installed two pile caps, three pillars and three panels along the elevated path. Only one final section of the ramp remains. We continued to install drains and rock walls. Mains power was disconnected to Collins Bridge, and we installed solar lighting. We continued planting works to stabilise and revegetate the embankment. ![]() Solar powered lighting has been installed on Collins Bridge Next stepsWork is underway on the construction of a retaining wall. This will allow us to install the final section of the ramp. We are also installing handrails on the ramp and stairs. Planting continues on the south side of Collins Bridge. ![]() Native vegetation have been planted on the north side of Collins Bridge. More is planned for the south side of the bridge. AccessConstruction work between the stairs and the street level are starting shortly. To keep everyone safe, there is no pedestrian access via the stairs to Gipps Street. Stay up to dateFor more information on the project please visit the Parks Victoria website. You can also contact Parks Victoria on 13 1963 or email engage@parks.vic.gov.au. Parks Victoria, Level 10, 535 Bourke St, This email is being distributed using Campaign Monitor, you can read their privacy policy here - campaignmonitor.com/policies/#privacy-policy |