Banks Peninsula storm roading updatesCouncil contractors are continuing work to repair a number of roads in Banks Peninsula that were damaged after significant rainfall on 15 and 16 December 2021. The following newsletter provides an update on the status of roadworks in several Banks Peninsula bays. A number of you should now have light vehicle access to your properties and work continues to improve the quality of these connections for residents. The purpose of this newsletter is to provide some clarity around the extent of the damage and the anticipated timelines for repair. Heavy rainfall this week made it difficult for our contractors to undertake repairs safely at some sites. Fulton Hogan will be working over the weekend to prevent further delays to the roading repair in the affected bays. The weather forecast for the coming week is looking promising and should allow us to stay on top of programme timelines. Big Hill RoadOriginal damage Scouring and dropouts What had to be done to make it safe? Worst scouring has been repaired. What still needs to be completed? Scouring and dropout repairs. Timeframe for this work to be completed Planned to be completed within a month. Current state of the road Fully open.
Dalglishs RoadOriginal damage Various small slips, three road dropouts and flooding at the bottom of the road. What had to be done to make it safe? Slips have been removed and path cleared through the silt. What still needs to be completed? Remaining silt and slips removed. Road dropouts repaired. Timeframe for this work to be completed Two months. What is the current state of the road? Fully open. Flea BayOriginal damage Various flooding debris, one large debris flow and one blocked culvert that caused damage to the seal. What had to be done to make it safe? Slips and debris have all been removed. A temporary ford and twin 600mm culverts have been installed. What still needs to be completed? Repairing the road drop out, road metaling and culvert works. Timeframe for completion 2 -3 weeks. What is the current state of the road? Fully open.
Goughs BayOriginal damage Various full length slips, dropouts on the bottom half with full road dropout approximately halfway down. What had to be done to make it safe? A path has been cleared through all slips to the main slip. Quad bike access has been created for all residents below the slip. What still needs to be completed? Work is underway on creating four-wheel-drive access for all residents. Slip clearing below the main slip to the bottom. Repairs to culverts and dropouts below the main slip. Design and construction of a solution for the main dropout. Timeframe for completion Slips are planned to be cleared within a month and culverts over the next three months. A design solution for the main dropout has now been submitted for approval to move to the construction phase. We will be consulting with land owners soon. What is the current state of the road? Gated with resident and farm only access. Hickory BayOriginal damage Various slips full length and one main drop out halfway. What had to be done to make it safe? A path has been cleared through all slips. A number of culverts have been repaired What still needs to be completed? Clear remaining slip material, replace damaged culverts and repair dropout. Approximately 50% of the work is completed. Timeframe for completion Work is expected to be completed within a month. What is the current state of the road? Gated with resident and farm only access. Considering opening the gates over the weekend once we are further through the repairs. Lavericks BayOriginal damage Severe scouring and slips on Lavericks Ridge Road. What had to be done to make it safe? Slips cleared and most of the scouring has been filled. What still needs to be completed? Filling of scouring and potentially more metal added to the road. Timeframe for completion Work is expected to be completed within a month. What is the current state of the road? Fully open. Le Bons BayOriginal damage Various flooding debris, one large debris flow and one blocked culvert that caused damage to the seal. What had to be done to make it safe? Slips and debris have all been removed except one which we are waiting on Orion to install a pole next to it. A temporary pavement repair has been made to the seal damage pending the end of the landfill clearing works. What still needs to be completed? Prepare and seal damaged sealed area. Clear last slip. Timeframe for completion Work is expected to be completed within a month. What is the current state of the road? Fully open. Le Bons Valley Road
Original damage Significant scouring, slips and dropouts. Significant damage to the second bridge What had to be done to make it safe? Access has been made through the scouring and slips. A temporary ford with twin 450mm culverts has been installed. Temporary repairs have been made to the bridge so it can be used in an emergency for light vehicles What still needs to be completed? Slip removal, scouring and road dropout repairs. Design and repair of the bridge. Timeframe for this work to be completed Slip repairs are planned to be completed within a month. The bridge repair is likely to take 2-3 months Current state of the road Fully open. Long BayOriginal damage Various small and large slips full length from Fishermans Bay Road, large dropout above Paua Bay Road and various slips. What had to be done to make it safe? A path has been cleared through all slips. What still needs to be completed? Clear remaining slip material, approximately 50% of this is completed. Design and repair of main slip. Timeframe for completion Slips are planned to be cleared within a month. Planning is underway on the best way to fix the main slip and we will have a clearer picture within the next few weeks. What is the current state of the road? Gated with resident and farm only access. Stony BayOriginal damage Severe scouring and slips on the outer side of the harbour. What had to be done to make it safe? Slips cleared and worst scouring filled. What still needs to be completed? Metal build up on the bottom end of the road along with a couple of culvert replacements. Timeframe for completion Work is expected to be completed within three months. What is the current state of the road? Fully open. Stay UpdatedDue to the complexity of the repairs required, particularly regarding Goughs Road, work will continue for some time. If you wish to stay updated on progress you can subscribe to our newsletter at www.ccc.govt.nz/bankspeninsula. Newsletters will be sent on a regular basis and will also be posted to the webpage once they are sent. Please be assured that we are doing all we can for all residents affected in the Peninsula area. If you have any other questions please don’t hesitate to contact us via transport@ccc.govt.nz. You received this email because you are subscribed to receive updates from Christchurch City Council. |