Hornby Centre update – June 2022

Two thumbs up for progress on site

Earlier this month the Waipuna Halswell-Hornby-Riccarton Community Board, representatives from local schools, site neighbours and Council staff visited the Hornby Centre site to see how work is progressing.

Construction company Naylor Love showed the group of around 25 around the site of the new facility. Once completed, the 4000 square metre centre will include a library, creative activities room, a lane pool, a hydrotherapy pool, a learn-to-swim pool, a toddlers’ wet play area, a spa pool and a customer services zone. 

 

Progress update - piling complete

Last week the 184th steel pile was driven into the ground, cut down to size and fitted with weld plates, marking a milestone for the construction of the Hornby Centre. Piling is now complete across the entire facility, including the 27 piles needed for the hydrotherapy pool.

Pictured above, on the left, the main pool area is shown, with piles completed and gas-proof membrane installed. On the right, the hydrotherapy pool area is shown, before the piles were cut down to size.

 

Help us plan the activities, programmes and events on offer at the Hornby Centre

The Council is opening two new centres towards the end of 2023.

Parakiore will be Aotearoa-New Zealand’s biggest sport and recreation centre, including pools, hydro-slides, indoor courts and more.

The Hornby Centre will be a combined recreation and sport centre, library and service centre.   

We’re now planning how to bring these spaces to life and what activities, programmes and events we’ll offer.

Help us plan by filling in the survey. It should only take around 5-10 minutes to have your say.

The survey will help us understand what people want from our recreation and sports centres – our two new centres and our existing centres. It’s a chance for you to have a say on the activities and programmes we offer and to suggest new ideas for us to consider. 

Have your say before Sunday 31 July and leave your email address at the end of the survey and be in to win one of 10 double passes to He Puna Taimoana: New Brighton Hot Pools.

Take the survey
 

Stay updated

Check here for background information on the Hornby facility project. If you know anyone who's interested in the project, they can sign up to this newsletter there.

Email hornbyfacility@ccc.govt.nz if you have any questions.

Are you on Facebook? If so, visit the Council Facebook page and hear breaking news as it happens.

It's easy to talk to us – follow us on Facebook, Twitter, call 941 8999, or talk to your Community Board members.

 
 
Christchurch City Council Facebook
 
Christchurch City Council Twitter
 

You received this email because you are subscribed to updates from Christchurch City Council. 

 Privacy policy.

 
 
Christchurch City Council
53 Hereford St, Christchurch Central City, Christchurch 8013
Preferences  |  Unsubscribe