Rangiriri update - May 2015
   

Earthworks on the Rangiriri section have been posing some challenges for the contractor on the project.

Although most of the 1 million cubic metres of earth to be moved is now complete the contractor is behind where they need to be for finishing the section by late 2016.

Highly variable, low strength soils with high water content in places have meant the contractor has had to do a lot of conditioning work using lime and cement. A lot of earth which was going to be used as fill on the project has had to be discarded and more suitable soil brought in.

This means the completion date of late 2016 is going to be a stretch.

Read the latest project update here including:

• Watch for traffic management changes at Rangiriri
• Cultural plans move ahead
• Landscaping and plans for planting
• Plenty of interest at open day

Story
 
Back to top
 
Info For general enquiries or contact information about the Waikato Expressway please visit our website www.nzta.govt.nz/waikato-expressway or email waikatoexpressway@nzta.govt.nz or ‘like’ us on Facebook.
 
Twitter Facebook YouTube
 
 
 
© 2009 – 2015 NZTA. All rights reserved. Privacy Policy | Legal disclaimer | Copyright

You have received this email because of previous communications with the NZ Transport Agency. If you no longer wish to receive these emails you can choose to unsubscribe here

If you received this email from a friend, sign up to receive this newsletter
New Zealand Government