View online |
![]() |
![]() |
TREC Tairāwhiti recovery updateIssue 25 |
![]() |
![]() |
11 July 2025 |
![]() |
![]() |
Tēnā koeIn this edition, you can read about a recently completed project on State Highway 2 (SH2), progress at Tōrere on State Highway 35 (SH35) as well as the latest at Hikuwai Bridge. We also share how TREC has been out in the community at Te Karaka and give a reminder around wandering stock and who to call. Thanks for your patience as we continue our recovery mahi. |
![]() |
![]() |
Completion at SH2 RakauroaCrews have now completed repairs to an underslip at Rakauroa on SH2 north of Otoko Hill. Cyclone Gabrielle had washed away the road shoulder creating an incredibly steep terrain, which presented challenges for the team. Soil nails were installed to stabilise the ground beneath the road and a shotcrete (sprayed concrete) retaining wall was constructed with a type of concrete that helps to drain water easily. The finished wall is 3.7m high and 15m long. Megaflo drains were also installed to reduce the water pressure behind the wall. These are flat with a large surface area to collect water; they drain faster and take up less space than traditional pipes. Once the retaining wall was complete the guardrail was reinstated. Crews have completed repairs at an underslip north of Otoko Hill on SH2. The green showing in the ‘after’ image is hydroseeding – a mix of water, seeds, mulch and fertiliser to reestablish vegetation. |
![]() |
![]() |
![]() |
SH35 Tōrere progressing wellWe’re making good progress at the SH35 Tōrere site with less traffic during the school holidays. The crew will soon begin repairing the overslip above the road and will also continue to work on the underslip below the road. When work on the overslip begins, traffic management will move from a priority give way to a 2-way single lane stop/go. We’ll install erosion and sediment controls at the base and then excavate the top of the overslip to reduce weight and ensure safe working conditions. An access track into the overslip will be dug out and stabilised with aggregate (gravel/stones), and a safety fence installed to protect from falls. The foundation work for the first retaining wall at this site (an MSE wall – mechanically stabilised earth) will begin to create a strong, safe slope that can support new drainage systems. This work will mark important progress in the safety and stability of this site. Work is now underway on both the underslip and overslip at Tōrere. Pictured is the overslip. |
![]() |
![]() |
![]() |
SH2 Hakanui Straight team at local community dayTREC was pleased to join the Te Karaka community day on Sunday 29 June to update community and hapū on the work starting soon at the SH2 Hakanui Straight project (formerly called Nesbitt’s Dip). The community day was held at the Mahaki Tiaki Tangata Evacuation Site, officially opened last year; a site where food, shelter, and other services will be available for displaced residents should they need support in the future. Our team presented on the important upgrade to this 850-metre-long flood prone section of the highway. We’ll raise the highway by 3 metres, install new culverts (large pipes) and extend the Hakanui Stream culvert to handle higher water volumes and reduce the risk of future flooding. The work will make this section of highway stronger, safer, and more reliable for everyday travel and emergency response. A pohiri to mark the project start will be held in mid-July, with main construction expected to start in late July. TREC representatives presenting at the recent Te Karaka community day. |
![]() |
![]() |
![]() |
Hikuwai Bridge enabling works nearing completionEnabling works are wrapping up on the Hikuwai Bridge replacement project with only pavement completion and surfacing to be done on the 250m long temporary realignment of SH35. Crews are hoping for drier weather to get these works underway which should take a few days if conditions are favourable. Once this work is complete there will be some finishing touches such as line-marking, guardrail and signage installation before a traffic switch from the existing SH35 road to the new alignment. We expect this traffic switch to be low impact with minor disruption to road users. We will share details on any traffic impacts in this newsletter as we have them. Once the temporary road is complete, the team and local contractors will have finished the 3 major enabling works packages. Main works to get the bridge build underway will follow soon after, once the contractor for that work package is appointed. Construction of the temporary road is almost complete. |
![]() |
![]() |
![]() |
Wandering stock? Call 111Tairāwhiti communities are familiar with the issue wandering stock present on our roads. If you see livestock on the road in uncontrolled circumstances, police consider it an emergency and you should call 111 to report it. NZ Transport Agency Waka Kotahi (NZTA) in Southland recently shared a video telling one person’s story about the profound and long-lasting impacts wandering stock can have. |
![]() |
![]() |
State highway snapshotBelow is a snapshot of construction works either underway or coming soon. You can also view completed, current and future work sites on our interactive map. Here are some of the construction terms we use:
SH2 underway (link to Otoko map and web page)
SH2 coming soon
SH35 underway
SH35 coming soon
|
![]() |
![]() |
![]() |
Whakapā mai – Get in touchIf you spot an issue at a work site after hours, call 0800 4 HIGHWAYS (0800 444449). Sign-up to receive these regular newsletters:
Local road network Gisborne District Council is responsible for local roading recovery projects. More information. |
![]() |
|
|