Progress so far
Since commencing construction in February this year, road widening and retaining walls have been constructed at the southern entrance to the Dome Valley.
Widening to enable the installation of a right-turn bay into Sheepworld, turnarounds at Sheepworld and Christine Place, road side barriers and centre median safety barrier will be completed by mid-2020.
The second section of the safety project, south of Wayby Valley Road, got underway in September, with a widened centreline, flexible centre safety barriers and roadside barrier improvements programmed to be completed in 2020. There are also three new turnarounds and a retaining wall in this section of the project.
The remaining sections of the safety improvements project will get underway in stages from March 2020 with the project due for completion late-2021.
The image below shows road widening underway south of Sheepworld in preparation for safety barrier installation.
|