Holiday period shutdown
The project site will shut down over the Christmas/New Year holiday period from Friday 22 December until Monday 8 January 2024.
On Tuesday 12 December the traffic lanes will shift east at southern end.
New temporary barriers will be installed Monday 18 December for long-term safety protection between the public and work site.
The 50km/h temporary speed will remain in place, please drive to the conditions and sign posted limits. The team will carry out daily site checks, to ensure that everything is in order.
|