SH2 Wainui Road to Ōpōtiki latest news and Covid-19 works update
Kia Ora,
Firstly, we would like to acknowledge the past two weeks and the change to Covid-19 Alert Level 4. We understand it can be a tough time for many New Zealanders.
This newsletter will provide an update on the safety improvements project and outline our Covid-19 protocols as we move to Alert Level 3.
Project Update
We’re pleased to let you know our contractor, Splice Construction, has almost completed work on four of the seven sites we are upgrading as part of the first section of the SH2 Wainui Road to Ōpōtiki safety improvements project.
Splice has been busy prior to moving to Covid-19 Alert Level 4, finishing off the earthworks, road widening and laying new seal on sites three to six, through Waiōtahe. You can see where these are on the map below.
The next step will be to install roadside safety barriers. These will be put in as soon as Splice is able to get back on site. For more information about road side barriers, you can read about them here.
|