Activities next week (1 - 8 November)
Please note that these works are weather dependent and may be delayed.
During the day (from 7am to 6pm)
Zone 1 (from Pukaki Creek Bridge to East of Campana Road)
-
Asphalt paving on the existing carriageway between Waokauri Bridge and the Campana intersection.
-
Hydro-seeding and mulch are being laid on the batters from Waokauri Bridge to Pukaki Creek Bridge
-
Instalment of TL-4 concrete barriers at the west of Campana Road
-
Stormwater drainage is being laid on both sides of the road between Pukaki Creek Bridge and the airport viewing platforms
-
Installation of south side wire rope barrier from viewing platforms to Orrs Road
-
Base preparation for kerb and channel at the Aviation Security Entrance
-
Fence realignment at the north of Campana Road
-
Erosion and sediment controls on the north side of the site
-
Streetlight cable pull between Orrs Road and the Campana Road intersection and poles will start to be installed.
Waokauri Bridge
-
Finishing the backfill around the headstock at night
Zone 2 (from East of Campana Road to the SH20 interchange)
-
Finish drainage lines, both new and redesigned, along Zone 2 parameters.
-
Placing of SIL and subsoils with box cuts
-
Continuing installation of subsoil drainage
-
Continuing installation of combined service ducts on the north side of the site
-
Continue with laying of AC28 asphalt in front of Manukau Memorial Gardens.
-
Prep for laying of AC28 between Waokauri Bridge and Manukau Memorial Gardens
-
Installation of streetlights
Utilities (throughout the site)
-
Common services trench works continue west of Manukau Memorial Gardens on the northern side
-
Trenching is set to commence on the southern side laying new service ducts towards the Waokauri Bridge.
At night (all zones from 9pm to 5am, Sunday to Thursday)
-
Trenching works for drainage in the verge are ongoing
-
The main focus of nightshift is to continue the replacement of asphalt pavement along the existing carriageway
-
The road will be under either stop/go or full road closure traffic management.
There will be no through traffic from SH20 interchange to the Tom Pearce Drive roundabout. Please follow the posted detour signs on SH20B.
Safety
SH20B has introduced the following safety measures to protect all road and shared path users including two temporary signalised road crossings for people on foot and on bikes:
-
All traffic must turn left both into and out of properties and side roads. Manukau Memorial Gardens is exempt from left-turn movements
-
Vehicles turning into driveways and side roads on the southern side must watch for bikes and foot traffic on the temporary shared cycle and walking path
-
Night time detours will likely be in place from Sunday to Thursday between 9pm and 5am. Please follow the posted detour routes
-
The speed limit for SH20B is 50kph from Manukau Memorial Gardens to Tom Pearce Drive, except at crossing points and coned paving areas where the speed will briefly drop to 30kph. Please drive safely and allow extra time for your journey.
Looking Ahead
An ongoing comprehensive programme of night works is in place to enable trenching for utility services and ducting at multiple locations across SH20B. Posted detours will be in place. We apologise for any inconvenience and thank you for your patience.