Progress update
We have completed the enabling works at the northern and southern ends of the gorge and are making good progress further up the gorge to ensure the area is safe and stable before the heavy machinery arrives on site to undertake the permanent works.
Permanent works have begun at both ends of the gorge with the large piling rigs and cranes in place at both ends of the gorge. Eighty-three piles need to be drilled up to 27m deep into the ground in some places.
In addition, we have completed the installation of all permanent pile casings on slip A3 and the permanent spawl walls on slip A8.
This is a huge moment for the project and the teams on site, as both ends are now working on the permanent works on the mission towards the summit. Due to the amount of space required to safely operate these machines, part of this work is being undertaken at night to ensure that access can be maintained for the remaining sites during the day.
In addition to this major milestone, we are nearing the completion of the enabling works on 4 of the other critical slips (A3/A5/A8/A9). The teams have also been undertaking preventative work on 8 other sites in the form of rock spall walls.
Back in May we were excited to identify the presence of long-tailed bats (pekapeka-tou-roa) in the gorge following a survey that was undertaken in April. Automatic Bat Monitors were set up to measure their high frequency signals through special bat software. The colder months mean that there is less activity for the bats while they conserve energy, meaning that they are at a greater risk with any work around their habitats.
The confirmation of this ‘Threatened’ (Nationally Critical) and protected species, means that we are now able to identify potential areas for bat roosting and foraging, and prioritise these areas for safe management by avoiding them until they can be safely managed using appropriate vegetation removal protocols.
|