State Highway 20B Early Improvements Update

15 January 2021

Kia ora koutou,

State Highway 20B Project Updates keep you up-to-date with project progress and upcoming physical works on State Highway 20B (SH20B).

Story
 

 
Story

Happy 2021 from the SH20B team

The SH20B Early Improvements project team wishes you a Happy New Year as we resume major works along SH20B.

From Tuesday 5 January, we have been back at work planning and activating day and night works as we push to acheive the completion of major aspects of the project.

Activities over the next four to five months will include drainage, kerb and channel installation, local road construction, asphalting and line-marking, landscaping and fencing.

Key to the project will also include the set-up of two new signalised intersections, central barrier protection and the completiion of the wide new shared user paths. Civil engineering work on the Waokauri Bridge is scheduled for completion by early February.

Utimately, public transport will become an easier and quicker option for commuters with dedicated bus lanes ensuring resilient connections between the Puhinui Interchange and the Auckland International Airport.

We are looking forward to a busy and safe summer as we see the final shape of the new highway becoming operational. Thank you for your patience!

Story
 

 
Story

Project progress

Activities next week (17 - 24 January)

Please note that some works are weather dependent and may be delayed.

During the day (from 7am to 7pm)

Zone 1 (from Pukaki Creek Bridge to East of Campana Road)

  • Commission Street lights from the southern Viewing Platform to Pukaki Creek Bridge
  • Place sloped Channel at Northern Viewing Platform
  • Install street light ducts near Pukaki Creek Bridge
  • Install street lights on north side from Pukaki Creek Bridge to Orrs Road
  • Prepare for the new shared use path from Orrs Road to Pukaki Creek Bridge on the south side
  • Complete raising AIAL chamber lids
  • Install fence panels Orrs Road to the Aviation Security Gate
  • Chip seal verge and lay top soil by the shared use path - Orrs Road to the Aviation Security Gate
  • Install street light duct from near Pukaki Creek Bridge to Orrs Road on the north side
  • Install street light duct north-east of Campana Road
  • Continue excavation and top soil of Swale north-east of Campana Road
  • Place the second layer of asphalt north-west of Campana Road
  • Start preparation work for kerb at Campana Road north-east
  • Install the signal poles at Campana Road south

Waokauri Creek Bridge

  • Shared use path upstand works to be completed
  • Road widening works westbound of the bridge

Zone 2 (from East of Campana Road to the SH20 interchange)

  • Continue current drainage lines work
  • Begin drainage works east of the Black Bridge Nursery Puhinui Road entry
  • Locate and protect gas main opposite Manukau Memorial Gardens westbound via hydro vac.
  • Breakout of island bull nose at the SH20 interchange
  • Begin installation of shared use path underneath the SH20 overpass
  • Asphalt replacement at night between Manukau Memorial Gardens and SH20
  • Driveway works at night at 437 and 467 Puhinui Road 

Utilities (throughout the site)

  • Over 800m of street light ducting has been installed between Pukaki Creek Bridge and Orrs Road.
  • Approximately 75 per cent of the common service trench has been completed
  • The remaining common service trench between Prices Rd and the SH20 interchange is planned to start late January.

At night (all zones from 9pm to 5am, Sunday to Thursday)

The road will be under Full Road Closure Traffic Management

  • Asphalt pavement replacement continues along the existing carriageway between Pukaki Creek Bridge and Orrs Road and between Manukau Memorial Gardens and SH20 interchange
  • Road widening works will be completed between Campana Road and Prices Road on the northern side.

Safety

SH20B has introduced the following safety measures to protect all road and shared path users including two temporary signalised road crossings for people on foot and on bikes:

  • All traffic must turn left both into and out of properties and side roads. Manukau Memorial Gardens is exempt from left-turn movements
  • Vehicles turning into driveways and side roads on the southern side must watch for bikes and foot traffic on the temporary shared cycle and walking path
  • The speed limit for SH20B is 50kph from Manukau Memorial Gardens to Tom Pearce Drive, except at crossing points and coned paving areas where the speed will briefly drop to 30kph. 

Looking Ahead

An ongoing comprehensive programme of night works is in place to enable trenching for utility services and ducting at multiple locations across SH20B. Posted detours will be in place. We apologise for any inconvenience and thank you for your patience.

Please drive safely and allow extra time for your journey.

Story
 

 
Story

Contact us

Please call us at 0800 796 796 or email sh20B@nzta.govt.nz if you have any questions about the SH20B Early Improvements project.

Story
 

 
spacer

Project overview

spacer
 
 
Story

Waka Kotahi NZ Transport Agency and Auckland International Airport Limited are upgrading State Highway 20B for better and more reliable travel options with a new shared path and additional priority lanes between Pukaki Creek Bridge and State Highway 20.

This project will integrate with improved transport facilities within the airport precinct along SH20B and at the upgraded Puhinui Station Interchange.

The project is the first step of the Southwest Gateway programme to provide better public transport, walking and cycling facilities with safer and more efficient freight movements to, from and around Southwest Auckland.

Fulton Hogan undertakes this work on behalf of Waka Kotahi.

Key early improvements on State Highway 20B to be delivered by 2021 include:

  • A safe place for people to walk and ride bikes
  • Safety improvements including central median barrier protection, improved lighting and a reduced speed
  • Improved pavement, drainage and stormwater treatment
  • Two improved intersections at Campana Road and Manukau Memorial Gardens.