| View online |
![]() |
TREC Tairāwhiti recovery updateIssue 34 |
|
14 November 2025 |
Tēnā koeIn this edition, read about work to protect the Rotokautuku (Waiapu) Bridge near Ruatoria, new culverts going in to help protect State Highway 35 (SH35) at Rototahe from flooding, and check out how the willow wall at the Kemps Hill (SH35) site is growing. There's updates on some of our State Highway 2 (SH2) projects and we’ve also included a reminder to drive with care through work sites, following some recent risky behaviour. Thanks again for your support and patience as we carry out this important recovery mahi. |
||
SH2 Hakanui Straight project flood resilience - 2 lanes reopening this monthGood news for drivers: from 21 November, SH2 through the Hakanui Straight project will reopen to 2 lanes, reducing delays. This section has been down to one lane while crews installed culverts (large pipes) and built up the area around the highway. The upcoming traffic switch will move vehicles onto a newly raised section, allowing work to begin on lifting the existing highway - a key step in boosting flood resilience. The work is weather dependent, and dates may change if needed. What to expect:
Thanks for your patience and for driving safely through the site. We’re making real progress towards a more resilient SH2. Crews are currently focusing on earthworks to build up either side of the highway to existing road level, in preparation for the switch. Find out more in our latest media release. Work underway at the Hakanui Straight project. |
||
![]() |
||
SH35: Enabling (early) work underway at Rotokautuku (Waiapu) BridgeCrews have cleared vegetation and started preparation work under Rotokautuku (Waiapu) Bridge near Ruatoria, where part of the Waiapu riverbank was swept away during Cyclone Gabrielle. To stabilise the area, we’re placing 4-tonne rock bags along the slope, with 200 dolosse (large interlocking concrete blocks) on top to anchor everything into place. This layered defence will help reduce erosion and protect the bridge foundations. The 2 groynes (structures that stick out from the riverbank to help stop erosion) will be repaired too. A temporary coffer dam (watertight barrier) will be built in the river later this month to temporarily hold back the water from the work area. Fish will be safely relocated before major works begin. A reminder that there will be no river access under the bridge until work finishes in April 2026 (weather permitting). Want to know more? Check out our project information sheet. Crews are removing vegetation, creating access roads and setting up site at Rotokautuku (Waiapu) Bridge, ready for the next phase of repair and strengthening work. |
||
![]() |
||
SH35 Kemps Hill willow wall: before and after works progressOur ‘living wall’ of willow trees is helping stabilise the slope at Kemps Hill, after 3 underslips reduced the road to one lane. In the before photo taken earlier this year, you’ll see the willows laid out horizontally. This planting method encourages deep root growth into the hillside to help hold it together. In the after photo, the trees are now growing upright, their intertwining roots strengthening the hillside against erosion. Blackbee Contractors also reinforced the road here with engineered fill. TREC is planting willow walls at other locations in the region, including on our SH2 Matawai Road site. They’re a key part of our recovery work. Before and after photo of willow trees at Kemps Hill. |
||
![]() |
||
SH35: All go at Rototahe flood resilience siteWarm, dry weather has been on our side over recent weeks, and crews at SH35 Rototahe are making the most of it. Since work began last month, great progress has been made on site. The team has excavated the subgrade (the foundation layer beneath the road) down 2 metres ready to install 4 of the 6 new culverts (large pipes). In total, the site will feature 8 culverts, including 2 existing ones. Each culvert (pictured) measures 1.2 metres across. Once connected across the eastern lane, they will be nearly 12 metres in length. Once installed, they’ll play an important part in reducing flood impacts in this low-lying section of SH35. For more information visit the project website. Culverts being installed at Rototahe to help reduce flooding. |
||
![]() |
||
SH35 Mangahauini Gorge: river temporarily divertedA 500-metre stretch of the Mangahauini River has been temporarily diverted. This is one of the largest river shifts ever undertaken in Tairāwhiti and will allow crews to construct the new roughened channel to help steady the riverbed and protect the highway from erosion. On Friday 7 November, the river was carefully redirected so crews could continue placing concrete hanbars and complete piling to anchor the new structures. The river will return to its natural course, flowing over the new channel, in early 2026. Ahead of the diversion, ecologists and hapū kaitiaki led a methodical defishing process, relocating more than 500 fish and eels. Their work followed ecological best practice and cultural protocols to protect taonga species and minimise disruption to aquatic life. TREC environmental lead Dathan Proudlove says the scale of the diversion reflects the complexity of the site and the care taken to do it right. “River diversions are typically under 100 metres,” he says. “This 500-metre shift demanded detailed hydrological modelling, cultural partnership, and ecological precision. It’s not just about redirecting flow, it’s about working alongside nature, not against it.” The temporary river diversion (visible to the right of the sheet pile wall) allows crews to safely continue work in and around the Mangahauini River. |
||
SH35 Hikuwai Bridge updateCrews are excavating the abutments (bridge ends) for Pier A (northernmost abutment) and building crane and piling platforms at the Hikuwai Bridge site. Specialised machinery and metal pile casings are being transported up SH35. If you're driving through, please watch for the delivery trucks crossing and give them space to help keep everyone safe. 12-metre long sheet piles are being used to construct a temporary retaining wall at the southern end of the Hikuwai Bridge. They’re being driven up to 2 metres deep below ground. |
||
Road cone-zone: enter with caution and kindnessCrews are reporting instances of drivers speeding and running red lights at some of our work sites. It’s dangerous and disappointing. Please remember: The people working on our sites are mainly locals - your neighbours, your mates, your whānau. They’re all working hard on the region’s roads, and we want them to get home safely at night. We’re working with police and local community champions to help improve driver behaviour and continually reviewing our traffic management setups. You might wonder why road cones and other traffic controls in place even if work appears complete. These setups are often protecting you and our crews while materials settle, inspections are carried out, or follow-up work is scheduled. Please help keep everyone safe:
Let’s look after each other on the roads this summer.
|
||
Summer Roadworks – plan ahead, allow for delaysSummer is roadworks season. The warm weather and longer daylight hours make it the best time to get the most work done. NZTA is sending regular newsletters to keep you informed about all roadworks on state highways in Tairāwhiti.
|
||
State highway snapshotBelow is a snapshot of construction works either underway or coming soon. You can also view completed, current and future work sites on our interactive map. Here are some of the construction terms we use:
SH2 underway
SH35 underway
SH35 coming soon
|
||
![]() |
Whakapā mai – Get in touchIf you spot an issue at a work site after hours, call 0800 4 HIGHWAYS (0800 444449). Sign-up to receive these regular newsletters:
Local road network Gisborne District Council is responsible for local roading recovery projects. More information. |
||
|
||||||||||||||||||||||
|