What we have been up to in Stage 2
Good progress was made over winter completing the wick drains and installing the monitoring equipment. Wick drains provide drainage paths to remove water out of the ground, so it compresses and strengthens faster.
The preload bulk fill is complete for both the northern and southern approach. Over 90,000T of material was imported, placed and compacted. The northern approach preload is now at a 95% settlement phase, allowing us to start on deep stormwater drainage, batter trimming and shaping.
We’ve been doing more preparation such as:
-
ground improvement piling trials
-
utility investigations
-
service re-routing
-
assembly of temporary works bridge staging.
In our last update, we talked about how we’d started the Drilled Displacement Piling (DDP ) for ground improvements at the Otaika Creek bridge. In the early stages of this work, we came across unexpected ground conditions, which has made this type of piling method difficult We’ve had to come up with a new way to construct these piles. A lot of work is being done to get this sorted quicky, and we're still on track for completion in early 2025.
|