Peka Peka to Ōtaki Expressway

Express CONNECT

30 August 2022


 

Kia ora

Welcome to the August edition of the PP2Ō Expressway construction update. As we head into spring, we’re certainly experiencing the effects of La Nina across the country with unprecedented wet weather.

While it’s been challenging for our construction crews, they’ve been making the most of any good weather available. With all civil works complete, we’re now focused on completing the laying of asphalt and works such as shoulder/median construction, as well as safety barrier and signage installation.

Chris Hunt

It’s also been pleasing to see how well our stormwater and sediment control has stood up to the recent deluge of water. 

To keep works progressing and ensure minimal disruption to traffic, we’re about to commence some night works, particularly at the north end of the project area. We’re certainly aware of the disruption to residents when these works are carried out, so will reduce the impact as best we can. 

Another milestone we’ve completed is the installation and testing of our electronic messaging signs for the expressway. These are located 1.5 kilometres before each of the off ramps and notify road users of road conditions ahead, journey times and other relevant information. They’re connected to the Wellington Traffic Operations Centre in Johnsonville.

On a cultural note, we’ve commenced discussions with local groups on how they can be involved in the expressway’s opening day which will be a great celebration of all the hard work that’s gone into the project. This month we’re also relocating our archaeological findings, some of which may end up in our time capsule. More on this below.

For further information on the project please visit our information centre (which has updated photos and brochures), visit our website www.nzta.govt.nz/pp2o, call us on 0800 PP2O INFO or email pp2o@nzta.govt.nz

Ngā mihi
Chris Hunt, Project Director

 

 

Left photo: Caleb Royal and Rawiri Rikihana of Ngā Hapu with archaeologist Emily Howitt. Right photo: some of the artefacts found during construction.

Archaeological findings provide historical insight

On any project like this, a lot of work goes on behind the scenes to collect and preserve historical items of interest that are found along the site as earth is moved.

Principal Archaeologist for the site, Emily Howitt, has been involved with the PP2Ō project even before consent for it was granted.

“My role has been to help get Archaeological Authority from Heritage New Zealand for the project. This is the equivalent to a Resource Consent but from an archaeological perspective,” Emily says.

Working with the environment team, Emily is now at the stage where she ensures all conditions of the Archaeological Authority are being met so a final report can be provided within 18 months of completion of the project.

“It's complex and a lot of work is involved including data collection, collating and preserving artefacts, and reporting and analysis. Iwi representatives from Ngā Hapu have been involved at every step of the way.”

Lots of old glass bottles have been found, along with remnants from daily activities carried out by those who once lived in the area such as fish/animal bones, shells, charcoal from fires and broken or worn-out tools

We look forward to sharing stories of the items selected for the time capsule with you when the collection and anaylsis of the artefacts is complete.

 

 

Night works at the northern end

Night works have commenced at the northern end of the project where the new off ramp ties into the top of County Road and the existing State Highway One. This involves the laying of sub-base material and deep levels of asphalt on top of it. We’re mindful of the noise and vibration impacts these works have on residents nearby, as well as bright light from the lighting towers and vehicles.

While it's ‘safety first’ at all times on site, particularly on an open State Highway, our teams are trying to reduce the impact of the works on residents as much as possible.

The north end of the current State Highway One will be under a stop/go traffic management system over the coming weeks from 7pm to approximately 5am as we carry out the works (timing will depend on the specific works each night).

If you have any questions about these works, please feel free to contact us on 0800 7726 4636 or pp2o@nzta.govt.nz

 

 

Free expressway maps

If you're keen to see the route of the expressway and where the on/off ramps are located, pick up a brochure – which contains a map – from our information centre. 

The information centre is located at 216 Main Highway Ōtaki and is open 9-5pm Monday – Friday, Saturday 9am-4pm and Sunday 10am-4pm.

View/download larger map

 

 

Community meetings

We continue to host our community group meetings bi-monthly with good community interest. 

Our next meetings are scheduled as follows:

• Community Liaison Group – 7pm, Monday 10 October, Ōtaki College.
• Northern Neighbourhood Group – 7pm, Monday 17 October, Waitohu School.
• Southern Neighbourhood Group – 7pm, Tuesday 18 October, Te Horo School.

 

 

Time capsule artefacts – keep them coming in!

If you would like to suggest an item to be considered for the time capsule, please email:

pp2o@nzta.govt.nz

 

 

Upcoming construction milestones

NORTHERN AREA

  • Deep lift asphalt paving between Ōtaki River and north to Waitohu Stream to be completed by mid-September 2022.
  • All wire rope barriers along the shoulders to be completed by the end of September 2022.
  • Local road works commenced in late August 2022 on Ōtaki Main North Road (SH1), north of the new expressway.
 

 

CENTRAL AREA

  • Wire rope barriers along the shoulders to be completed by the end of August 2022.
  • Winiata Link Road to be completed by mid/late October 2022.
  • Road surfacing of bridges is to commence in September 2022.
 

 

SOUTHERN AREA

  • Deep lift asphalt paving south of Mary Crest to be completed by the end of August 2022.
  • Wire rope barriers along the shoulders to be completed by mid-September 2022.
  • The final layer of the road surface, EMOGPA, is to commence late September/early October 2022.
 

 

Staff activity drives home health and safety messages

Once a month we get together early in the morning for Health and Safety training.

This month the team participated in a light-hearted activity invented by our Health and Safety team. It was designed to get us thinking about how we plan our work, follow our plans, and manage incidents and environmental changes in a timely manner.

The task was to build a tower using marshmallows and spaghetti while managing imaginary environmental challenges and constraints such as earthquakes, Covid 19 outbreaks and weather disruptions.

A lot of fun and important reminders were shared, as well as a few impressive towers built to start the day!

 

 

More information

 
 

For more information on the Peka Peka to Ōtaki Expressway, contact us at 0800 7726 4636 or email pp2o@nzta.govt.nz

Visit our website www.nzta.govt.nz/pp2o