Progress update
Works on the project continue at pace, and if you drive through the area you’ll notice lots of progress visible from the road. Over the last 3 months the team have been busy preparing to construct Otaika Bridge, completing ground improvement works and constructing retaining walls.
To keep up the great pace, in April, we had 4 piling machines operating at the same time. We have now installed 600 Rammed Aggregate Piers (RAPs) at the Otaika Bridge abutments. Abutments are the structures at the ends of a bridge span that support its structure. See more on RAPs and why we use them in our spotlight section below.
Work on the retaining wall is progressing well, temporary sheet piles were placed in March and the excavation and construction of the piling platform prepared. In April, 50 reinforced 750 millimetre diameter concrete piles were installed along the Otaika Creek, where a 60 metre by 2 metre high capping beam will be formed - this increases the strength of the foundation before adding in the concrete. Three pours of concrete will be completed by the end of July.
In early June, we deployed a 250 tonne Crawler crane, known as "The Rainbow Warrior," to start building the southern side of the Otaika Bridge. A 300 tonne crawler was added in early July to service the northern side. These cranes will manage the bridge construction over the next 6 months. The heaviest lift will be about 42 tonnes (about the same weight as 30 cars) for the central bridge span!
At the end of this month, another big milestone will be achieved with the completion of the southern pier and abutment piles for the bridge. The piles are 1500 millimetre diameter, with permanent casings, installed at a depth of 15-22 metres into the bedrock below. The pier piles are out in the Otaika Creek and require temporary staging to enable the 85 tonne piling rig to get into position and drill down. The rock is very hard and requires tools with cutting teeth to grind and break up the rock.
|