Small test pit investigations recently completed at Oromahoe, just south of Kerikeri. These investigations check the ground beneath the road to understand its condition and help us design the best, most durable treatments for future road upgrades.
 

Small test pit investigations recently completed at Oromahoe, just south of Kerikeri. These investigations check the ground beneath the road to understand its condition and help us design the best, most durable treatments for future road upgrades.

Kia ora and welcome

Welcome to the first edition of the Northland state highway maintenance roadworks update for the 2025/26 summer season. In this e-news, we’ll share updates on maintenance and renewal roadworks across the state highway network from Topuni all the way to Te Reinga Wairua (Cape Reinga).

With our summer maintenance programme set to begin in September, we’ll share weekly updates with you to let you know what work is happening on our state highways, where it’s happening and when, to help you plan your journey.

Over the coming months essential maintenance work including road rebuilding and resurfacing will be carried out across the country. To be effective and durable, this work must be done during the warmer, drier months. It can't be done during winter when the weather is wet and cold.

While the season hasn’t officially begun, we’re already busy with preparation works. Below we share some of the works underway to help us prepare for the season.

We’ll share more details about the full 2025/26 programme in the coming weeks.

Please encourage family and friends to sign up to stay up to date with works happening on state highways in the region. 

Whenever you come to a worksite, remember that our road workers are doing their best to complete their work and keep you moving. Please be respectful and follow their advice and instructions.

We know roadworks can be disruptive, and we appreciate your patience while we carry out these improvements.

Stay updated on road conditions before you travel at:  https://journeys.nzta.govt.nz/.

Ngā mihi nui,
The NZTA Northland team

 

Mill and fill repairs south of Dargaville. An asphalt mill and fill repair involves removing the top layer of worn asphalt or chip seal, then laying and compacting new asphalt to restore the road surface.
 

Mill and fill repairs south of Dargaville. An asphalt mill and fill repair involves removing the top layer of worn asphalt or chip seal, then laying and compacting new asphalt to restore the road surface.

Preparing Northland’s roads for the next renewal season

In the lead up to the 2025/26 road renewal season, our maintenance crews are carrying out important preparation works across the region.

From 11 to 29 August (weather permitting), you’ll see five roadwork crews working day and night under short stop/go traffic management along SH12 (sections between Paparoa and the Brynderwyn Hills) and SH1 (sections north and south of Whangārei).

This is essential prep work ahead of a busy renewal season where we plan to rebuild, resurface and reseal a range of roads around the region, using chipseal or new asphalt at several sites. Before this larger resurfacing can begin, roadworkers often need to complete pre-seal repairs and patching. That’s why you might see or hear about work happening in the same spots twice – the first visit strengthens the road base and addresses defects, so the final resurfacing lasts longer and provides a smoother, safer drive.

Roadworkers will be digging out and rebuilding weak sections, strengthening road foundations with stabilising agents, and replacing worn asphalt. Doing this now protects the highways from further damage and means resurfacing projects starting in spring can be delivered more efficiently, giving communities safer, longer lasting roads.

 

 

Upcoming roadworks

State highways with scheduled works this week:

  • SH1 – Towai, Kauri, Oakleigh, Brynderwyn Hills and Topuni
  • SH12 – Paparoa
  • SH14 – Dargaville

Note: Roadworks may be postponed due to rain or other factors that disrupt the weekly schedule.

Check the NZTA Journey Planner for the latest travel information and journey times before starting your journey: https://journeys.nzta.govt.nz/.

Information current as at 2:42pm on 08.08.2025.

 

 

State Highway 1 - Kawakawa to Cape Reinga

No significant works scheduled for this week.

 

 

State Highway 1 – Whangārei to Kawakawa

State Highway 1 – south of Towai Road to north of Ruapekapeka Road, Towai

  • Monday 14 July to November, during the day, 6am – 6pm.
  • Due to drainage enabling works in preparation for a road rebuild, stop/go traffic management and speed restrictions will be in place.
  • Stop/go traffic management will be in place at Towai Road and Ruapekapeka Road intersections (day crew: 7am – 5pm; night crew: 5pm – 5am).

State Highway 1 – Kauri

  • Tuesday 12 August to Wednesday 13 August, during the night, 8pm – 5am.
  • Due to mill and fill works, one lane closure with stop/go traffic management and speed restrictions will be in place.
 

 

State Highway 1 - Topuni to Whangārei

State Highway 1 – Oakleigh

  • Sunday 10 August to Thursday 14 August, during the night, 8pm – 5am.
  • Due to pre-seal repair works, one lane closure with stop/go traffic management and speed restrictions will be in place.

State Highway 1 – Brynderwyn Hills

  • Sunday 10 August to Thursday 14 August, during the night, 8pm – 5am.
  • Due to pre-seal repair works, one lane closure with stop/go traffic management and speed restrictions will be in place.

State Highway 1 – Topuni

  • Wednesday 13 August to Thursday 14 August, during the night, 8pm – 5am.
  • Due to pre-seal repair works, one lane closure with stop/go traffic management and speed restrictions will be in place.
 

 

State Highway 10

No significant works scheduled for this week.

 

 

State Highway 11

No significant works scheduled for this week.

 

 

State Highway 12

State Highway 12 – Paparoa, between Nurse Cavell Lane and the intersection of SH12 & SH1.

  • Monday 11 August to Friday 29 August, during the day, 7am – 6pm.
  • Due to pre-seal repair works, one lane closure with stop/go traffic management and speed restrictions will be in place.
 

 

State Highway 14

State Highway 14 – Awakino River Bridge, Dargaville

  • Monday 11 August to Friday 18 August, during the day, 8am – 6pm.
  • Due to minor road resurfacing and removal of scaffolding for bridge strengthening work in this area, stop/go traffic management and speed restrictions will be in place.
 

 

State Highway 15

No significant works scheduled for this week.

 

 

More information

 
 

Please be aware that there may be other less disruptive state highway works not listed in this newsletter.

For more information on Northland/North Auckland state highway maintenance, contact us at info@nzta.govt.nz or 0800 4 HIGHWAYS (0800 444 449)

Visit our website: www.nzta.govt.nz/northland-state-highway-maintenance-programme/

For information about what’s happening with other infrastructure projects across the region please visit the Northland projects page here: https://www.nzta.govt.nz/projects/regions/1203