From Monday 15 April weekday road closures will resume on Queen Charlotte Drive between the Picton Lookout and Shakespeare Bay from 9am to 3pm, with openings on the hour every hour. There will be delays of up to 10 minutes between 7am to 9am at this location. These closures are for Port Marlborough to undertake logging operations and the removal of wilding pines and wattles.
There are multiple recovery sites under construction along the length of Queen Charlotte Drive. Work at these sites will be under stop/go traffic management, please expect delays.
Crews have been working on the construction of a MSE (Mechanically Stabilised Earth) wall and associated drainage upgrades on Queen Charlotte Drive (approximately 1.7km from the SH6/Havelock turnoff) near Cullen Point, Mahakipawa Hill.
This week crews have started building the drainage base of the new wall. Next week crews will continue building the MSE wall from the base upwards.
Work to install a new culvert and repair the road continues, just prior to Moenui Road when travelling from Havelock. Last week the last sections of the culvert were installed upstream. This week work will continue to install the wing walls on the outlet and reshape the ground upstream.
A new railway iron site, 450m before Moenui Road, when travelling towards Picton is scheduled to commence in the next two weeks.
The construction of two railway iron walls, approximately 1.9km and 2.1km past Tepuia Heights, on Queen Charlotte Drive when travelling towards Picton, is close to completion. Sealing is scheduled to be completed early next week. Users of the Link Pathway will be guided through these sites by traffic management.
Work is being undertaken 750m past The Grove Jetty, when travelling towards Picton to complete drainage upgrades and repair a dropout. This week a new culvert was replaced and pavement reinstatement works started.
Work continues 450m past Aussie Bay. There are two new retaining walls under construction at this site. This week crews poured concrete for the new kerb at the first wall and sealing is scheduled to be undertaken next week. At the second retaining wall site, the old wall was removed this week, with anchor drilling starting next week.
Work to realign the road and repair a slip continues 70m past Governors Bay when travelling towards Picton. Last week crews laid mesh and applied shotcrete to the slope of the slip.
Please note there will be increased truck movements while work is being carried out. Please plan ahead for delays.
Please keep to the reduced temporary speed limits when you're travelling through our worksites to ensure the safety of crews and road users. We thank you for your patience.
|