There are multiple recovery sites under construction along the length of Queen Charlotte Drive. Work at these sites is under stop/go traffic management, please expect delays.
Crews have been working on the construction of a Mechanically Stabilised Earth (MSE) wall and associated drainage upgrades on Queen Charlotte Drive (approximately 1.7km from the SH6/Havelock turnoff) near Cullen Point, Mahakipawa Hill.
This week crews have finished rock work at the bottom of the slope. This week and next crews will continue building the MSE wall from the base upwards.
Work to install a new culvert and repair the road continues, just prior to Moenui Road when travelling from Havelock. Last week work to install the wing walls on the outlet and reshape the ground upstream was undertaken. This week, crews will continue to build the culvert inlet upstream.
A new railway iron wall site, 450m before Moenui Road, when travelling towards Picton is scheduled to begin next week.
The construction of two railway iron walls, approximately 1.9km and 2.1km past Tepuia Heights, on Queen Charlotte Drive when travelling towards Picton, is close to completion. Sealing and the installation of site rails has been carried out this week. Users of the Link Pathway will continue to be guided through these sites by traffic management.
Work is being undertaken 750m past The Grove Jetty, when travelling towards Picton to complete drainage upgrades and repair a dropout. Last week a new culvert was replaced, this week road preparation and sealing has been undertaken. The site is scheduled to be completed by the end of the week.
Work continues 450m past Aussie Bay. There are two new retaining walls within this site. Last week, the kerb was poured and water channels cleared at the first wall. This week crews carried out road preparations. At the second retaining wall site, the old wall was removed last week and anchor drilling began this week.
Work to realign the road and repair a slip continues 70m past Governors Bay when travelling towards Picton. Last week crews laid mesh net down the slip face. Next week crews will work on a partial retreat requiring earthworks.
Please note there will be increased truck movements while work is being carried out. Please plan ahead for delays.
Please keep to the reduced temporary speed limits when you're travelling through our worksites to ensure the safety of crews and road users. We thank you for your patience.
|