SH73 West Melton intersection improvements - reminder of work starting next week
Kia ora
The work this week, to rebuild the SH73/Weedons Ross Road south intersection, has gone to schedule and the intersection will reopen before Monday.
We know this work has been disruptive and thank you for your understanding and patience.
Reminder: from Monday16 January
The bulk of the remaining work is on Weedons Ross Road and West Melton Road to the south of SH73.
Traffic impacts
From Monday 16 January for two weeks, the northern entrance to Kingsdowne Drive will be closed.
From Monday 16 January for five weeks, the new link road will be closed.
Two way traffic will be reinstated on West Melton Road and Weedons Ross Road during this time with some sections on both roads temporarily controlled with traffic lights.
We’ll ensure access for emergency services is maintained.
Read more about the work in our last project update, including a map of the temporary traffic management system here
or
Read the works notice here
Thanks again for your understanding and patience.
Ngā mihi (Kind regards)
The project team
|