Waka Kotahi NZ Transport Agency

SH10 Kāeo Bridge upgrade

28 September 2023


 

Kia ora koutou,

Winter has been a busy time at Kāeo Bridge and we are now heading into Spring with an almost fully-formed bridge.

 

 

Bridge construction update

Most of the concrete deck has been poured, with a fourth span (section) to be completed next. Each span is 30m long and takes a total volume of 76m3 of concrete.  Work is also continuing on the two abutments, these are structures that connect the deck of the bridge to the ground. Other remaining work includes installing guardrails and applying an asphalt layer to the deck, on top of the concrete pour.

 

 

Change of road layout

The layout of the road south of the bridge changed on Monday 25th September. The old temporary road has become our construction area.

Traffic now travels through what was our work zone, making a straight line to the existing Kāeo Bridge. Please take care when driving through the site and allow some time for motorists to adjust to the change.

 

 

A render of the finished Kāeo bridge

Pavement and roundabout works

For the remainder of 2023 our focus will be on building the roundabout (Kāeo side of the bridge) and the new roads that approach the intersection. This includes lengthening Whangaroa Road to meet the roundabout. Pavement construction will happen in stages, with various layers of material and metal applied to build up a strong road. Each layer is tested before the next can be applied. The final stage is chip sealing or asphalt application, followed by line marking and installing guardrails and lighting.

 

 

More information

 
 

If you have any concerns or queries about construction works, please call Mel Norris from Fulton Hogan on 0800 577 623.

Road users can also contact Waka Kotahi NZ Transport Agency at any time on 0800 44 44 49.